358 Brannan St
San Francisco permit 202210214853 · Financial District/South Beach
To comply w/city planning complaint #2020088enf, remove storefront & brannan facade, legalize varney place facade
- Filed
- Oct 21, 2022
- Issued
- Dec 26, 2023 (14 months after filing)
- Completed
- Mar 21, 2024 (3 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 7 stops across 4 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Oct 21, 2022 | Oct 21, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 21, 2022 | Feb 8, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jan 20, 2023 | Jan 20, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 1, 2023 | Mar 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 29, 2023 | Mar 29, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2023 | Dec 5, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 26, 2023 | Dec 26, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $16,000
| Name | Role | License on permit |
|---|---|---|
| Ernest Hartley Selander Selander Architects | Architect | C12715 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026