2530 14th Av
San Francisco permit 202210244973 · West of Twin Peaks
1st fl:remove & replace(e)interior stair with a (n)stair to 2nd fl. 2nd fl:interior remodel,kitchen,full bath, add 1/2 bath,remove bedroom,new stair to 1st & 3rd fl.3rd fl:add bed and full bath to (e)fl,new stair to 2nd fl.
- Filed
- Oct 24, 2022
- Issued
- Feb 13, 2024 (16 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 45 stops across 6 departments
- Comments issued
- 7 times, by Building Inspection, Public Utilities
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2022 | Oct 26, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 26, 2022 | Mar 31, 2023 | — |
Permit Processing Center Building Inspection · PPC | Oct 26, 2022 | Dec 19, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Feb 10, 2023 | Mar 31, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 31, 2023 | Sep 22, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 31, 2023 | Oct 2, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2023 | Apr 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 31, 2023 | Apr 20, 2023 | — |
Urban forestry Public Works · DPW-BUF | Apr 5, 2023 | Oct 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 22, 2023 | Sep 25, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 22, 2023 | Sep 26, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2023 | Sep 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2023 | Sep 26, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 28, 2023 | Oct 3, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 2, 2023 | Dec 11, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2023 | Oct 2, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 3, 2023 | Oct 4, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 6, 2023 | Oct 6, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 10, 2023 | Oct 10, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2023 | Feb 13, 2024 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 22, 2024 | Mar 1, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 26, 2024 | Feb 26, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 28, 2024 | Feb 28, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 29, 2024 | Feb 29, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Mar 1, 2024 | Mar 1, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 1, 2024 | May 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 1, 2024 | Apr 2, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 1, 2024 | Mar 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 1, 2024 | Aug 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 1, 2024 | Mar 5, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 1, 2024 | Sep 24, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 3, 2024 | Apr 3, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 25, 2024 | Apr 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 9, 2024 | Jul 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 29, 2024 | Sep 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 16, 2024 | Sep 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 17, 2024 | Sep 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2024 | Sep 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2024 | Sep 17, 2024 | Issued Comments |
Planning neighborhood notice Planning · CP-NP | Sep 19, 2024 | Sep 19, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 19, 2024 | Sep 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2024 | Sep 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 20, 2024 | Sep 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 23, 2024 | Sep 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 24, 2024 | Oct 16, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $417,000
| Name | Role | License on permit |
|---|---|---|
| Peter A Zepponi Zepponi Architects | Architect | C26699 |
| Nate Williams Mosswood Engineering | Engineer | C62068 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026