1231 19th Av #0
San Francisco permit 202210255103 · Sunset/Parkside
Addition of a 375 sq. ft. accessory dwelling unit (adu) to 1st floor of an existing 3-story, 6 unit apartment building under the state program.
- Filed
- Oct 25, 2022
- Issued
- May 17, 2023 (7 months after filing)
- Completed
- May 2, 2025 (24 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 35 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 25, 2022 | Dec 1, 2022 | — |
Code enforcement Building Inspection · CES | Nov 15, 2022 | Nov 15, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Nov 30, 2022 | Nov 30, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 1, 2022 | Mar 23, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 1, 2022 | Jan 31, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2022 | Dec 5, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 1, 2022 | Feb 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 1, 2022 | Feb 7, 2023 | — |
Urban forestry Public Works · DPW-BUF | Dec 1, 2022 | Apr 3, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 1, 2022 | Apr 28, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 31, 2023 | Mar 14, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2023 | Mar 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 13, 2023 | Mar 15, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 13, 2023 | Mar 16, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 23, 2023 | Apr 27, 2023 | — |
Development fee collection Building Inspection · DFCU | Apr 28, 2023 | Apr 28, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 28, 2023 | May 17, 2023 | — |
Addendum 1: Arch, t-24, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 2, 2023 | Aug 3, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 3, 2023 | Sep 18, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 3, 2023 | Aug 18, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 3, 2023 | Aug 7, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 3, 2023 | Nov 30, 2023 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2023 | Sep 25, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 21, 2023 | Sep 28, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 18, 2023 | Nov 3, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2023 | Oct 25, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 30, 2023 | Oct 30, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 3, 2023 | Nov 3, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2023 | Nov 6, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 8, 2023 | Nov 28, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 8, 2023 | Nov 9, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 8, 2023 | Nov 8, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 8, 2023 | Nov 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 8, 2023 | Nov 9, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 30, 2023 | Dec 6, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $119,262
| Name | Role | License on permit |
|---|---|---|
| Robert Eric Smith Smithworks Engineering | Engineer | S5679 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024