42 Clipper St
San Francisco permit 202210255153 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Alter site permit pa201912190060 for rev desc:"renovation and add'n to (e) 2-unit building w/in (e) footprint.convert (e) garage to habitable space,add (n) garage underneath 1/l.(n) 690sf horizontal add'n on 3/l.renovated bldg to contain entry foyer, kitchen, lr, dr, study, 2beds, 2baths, 1wc...
- Filed
- Oct 25, 2022
- Issued
- May 12, 2023 (7 months after filing)
- Completed
- Not completed yet
- Review stops
- 29 stops across 5 departments
- Comments issued
- None
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 25, 2022 | Oct 25, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 27, 2022 | Nov 1, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 2, 2022 | Dec 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 22, 2022 | Nov 29, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 1, 2022 | Dec 16, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 16, 2022 | Jan 5, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 5, 2023 | Feb 6, 2023 | — |
Urban forestry Public Works · DPW-BUF | Feb 2, 2023 | Feb 2, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2023 | Feb 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 8, 2023 | Feb 23, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 23, 2023 | Mar 1, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 2, 2023 | Apr 20, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 31, 2023 | Apr 3, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 3, 2023 | Apr 4, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 5, 2023 | Apr 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 24, 2023 | Apr 24, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2023 | May 12, 2023 | — |
Addendum 1: Final architectural, structural, mechanical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 12, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | May 23, 2023 | Jun 13, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | May 23, 2023 | May 23, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 9, 2023 | Aug 9, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 13, 2023 | Jul 3, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 5, 2023 | Aug 17, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 27, 2023 | Jul 28, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 31, 2023 | Aug 3, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 3, 2023 | Aug 8, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 9, 2023 | Aug 11, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 18, 2023 | Aug 18, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 18, 2023 | Nov 16, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| P Casper Mork-Ulnes Mork-Ulnes Architects | Architect | C33031 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024