Scope of work
As written on the permit application.

Alter site permit pa201912190060 for rev desc:"renovation and add'n to (e) 2-unit building w/in (e) footprint.convert (e) garage to habitable space,add (n) garage underneath 1/l.(n) 690sf horizontal add'n on 3/l.renovated bldg to contain entry foyer, kitchen, lr, dr, study, 2beds, 2baths, 1wc...

Timeline
Key dates from the city record.
Filed
Oct 25, 2022
Issued
May 12, 2023 (7 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
29 stops across 5 departments
Comments issued
None
Put on hold
6 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 25, 2022—

Zoning review

Planning · CP-ZOC

Nov 1, 2022—

Building plan review

Building Inspection · BLDG

Dec 1, 2022—

Street use and mapping

Public Works · DPW-BSM

Nov 29, 2022—

Building plan review

Building Inspection · BLDG

Dec 16, 2022—

Building plan review

Building Inspection · BLDG

Jan 5, 2023—

Building plan review

Building Inspection · BLDG

Feb 6, 2023—

Urban forestry

Public Works · DPW-BUF

Feb 2, 2023—

Street use and mapping

Public Works · DPW-BSM

Feb 7, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 23, 2023—

Zoning review

Planning · CP-ZOC

Mar 1, 2023—

Urban forestry

Public Works · DPW-BUF

Apr 20, 2023—

Building plan review

Building Inspection · BLDG

Apr 3, 2023—

Zoning review

Planning · CP-ZOC

Apr 4, 2023—

Zoning review

Planning · CP-ZOC

Apr 13, 2023—

Permit Processing Center

Building Inspection · PPC

Apr 24, 2023—

Central Permit Bureau

Building Inspection · CPB

May 12, 2023—

Addendum 1: Final architectural, structural, mechanical

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

In progress—

Building plan review

Building Inspection · BLDG

Jun 13, 2023—

Structural plan approval

Building Inspection · PAD-STR

May 23, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Aug 9, 2023—

Building plan review

Building Inspection · BLDG

Jul 3, 2023—

Fire prevention review

Fire Department · SFFD

Aug 17, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jul 28, 2023Approved

Urban forestry

Public Works · DPW-BUF

Aug 3, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 8, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 11, 2023Approved

Permit Processing Center

Building Inspection · PPC

Aug 18, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Nov 16, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
P Casper Mork-Ulnes

Mork-Ulnes Architects

ArchitectC33031
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202210255153 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record