13 Eugenia Av
San Francisco permit 202210255159 · Bernal Heights
(e) 1st flr: bathrm remodel & replace in-kind damage siding. rough plumbing/elect/strcutural support & other damaged bldg assemblies. replace bathrm window. remodel unconditioned basement: lowering slab, pouring foundation, convert into habitable, extend into rear yard for office/bathrm/laundry rm..
- Filed
- Oct 25, 2022
- Issued
- Jun 5, 2023 (7 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 30 stops across 4 departments
- Comments issued
- Once, by Public Works
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 25, 2022 | Oct 26, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 26, 2022 | Mar 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Oct 26, 2022 | May 18, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 14, 2023 | May 5, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2023 | Mar 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2023 | Mar 17, 2023 | — |
Zoning review Planning · CP-ZOC | May 9, 2023 | May 9, 2023 | — |
Building plan review Building Inspection · BLDG | May 9, 2023 | May 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 9, 2023 | May 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2023 | May 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 18, 2023 | Jun 5, 2023 | — |
Addendum 1: Arch,struct,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 16, 2023 | Jun 16, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 16, 2023 | Aug 2, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 16, 2023 | Jul 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 16, 2023 | Aug 23, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2023 | Jun 20, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 16, 2023 | Oct 2, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 24, 2023 | Aug 18, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 18, 2023 | Aug 18, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 18, 2023 | Aug 18, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2023 | Aug 24, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 21, 2023 | Sep 6, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 6, 2023 | Sep 6, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2023 | Sep 29, 2023 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Sep 6, 2023 | Sep 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 6, 2023 | Sep 6, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 29, 2023 | Oct 2, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 29, 2023 | Oct 2, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 29, 2023 | Oct 2, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2023 | Oct 4, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $241,441
| Name | Role | License on permit |
|---|---|---|
| Dinesh Perera | Architect | C38857 |
| Erik Garcia Garcia Structural Design | Engineer | C87465 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026