364 Moscow St
San Francisco permit 202210265188 · Excelsior
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Recommencement and completion of work approved under pa# 201109074019. 50% of work remaining. new exterior deck with firewall on south edge. new raised floor at garage level. remove 2 non-compliant rear yard sheds. interior kitchen remodel, bath relocation, & wall reconfiguration at 2nd fl.
- Filed
- Oct 26, 2022
- Issued
- Mar 19, 2024 (17 months after filing)
- Completed
- Apr 16, 2025 (13 months after issuance)
- Review stops
- 27 stops across 4 departments
- Comments issued
- 7 times, by Building Inspection
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Oct 28, 1988 | Oct 28, 1988 | — |
Apartment and hotel inspection Building Inspection · HIS | Oct 26, 2022 | Oct 26, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 26, 2022 | Nov 2, 2022 | — |
Code enforcement Building Inspection · CES | Oct 31, 2022 | Oct 31, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 2, 2022 | Jun 22, 2023 | — |
Permit Processing Center Building Inspection · PPC | Nov 2, 2022 | Feb 27, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Feb 8, 2023 | Jun 22, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 22, 2023 | Jul 27, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 22, 2023 | Jan 26, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2023 | Jun 28, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 22, 2023 | Jul 12, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 4, 2023 | Aug 11, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 4, 2023 | Dec 19, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 17, 2023 | Aug 17, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 10, 2023 | Oct 11, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 7, 2023 | Dec 20, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 19, 2023 | Dec 19, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 26, 2023 | Dec 26, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 26, 2023 | Jan 2, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jan 16, 2024 | Jan 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 26, 2024 | Jan 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 30, 2024 | Jan 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 30, 2024 | Feb 1, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 30, 2024 | Jan 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2024 | Feb 14, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2024 | Feb 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2024 | Mar 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $237,070
| Name | Role | License on permit |
|---|---|---|
| Audrey A Bauer Studio Maven | Architect | C36620 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019