261 Amber Dr
San Francisco permit 202210265197 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
To comply with nov# 202293873. 2nd revision to pa# 201601257895. minor changes to exterior envelope. enlarge 1 bathroom window. add tempered glass to deck rail. extend upper 2nd fl into triple story air space to expand bathroom (+93 sf). redesign kitchen. enlarge skylight. change siding to shingle.
- Filed
- Oct 26, 2022
- Issued
- Jun 10, 2024 (19 months after filing)
- Completed
- May 13, 2025 (11 months after issuance)
- Review stops
- 67 stops across 5 departments
- Comments issued
- 14 times, by Building Inspection, Permit Center
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2022 | Jan 17, 2023 | — |
Building inspector Building Inspection · BID-INSP | Oct 26, 2022 | Nov 3, 2022 | — |
Code enforcement Building Inspection · CES | Jan 13, 2023 | Jan 13, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 18, 2023 | Feb 2, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 18, 2023 | Jun 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 6, 2023 | Nov 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2023 | Feb 8, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2023 | Feb 22, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 18, 2023 | Aug 21, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2023 | Aug 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 18, 2023 | Aug 23, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 1, 2023 | Nov 20, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 4, 2024 | Jan 5, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 12, 2024 | Mar 5, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2024 | Feb 8, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 12, 2024 | Jan 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 12, 2024 | Jan 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2024 | Jan 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 12, 2024 | Jan 25, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 13, 2024 | May 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 13, 2024 | May 14, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 13, 2024 | May 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2024 | May 20, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 22, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2024 | May 16, 2024 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | May 21, 2024 | May 21, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 21, 2024 | Jun 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2024 | May 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 21, 2024 | May 28, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 29, 2024 | May 30, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 29, 2024 | May 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 29, 2024 | Jun 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 29, 2024 | Jun 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 6, 2024 | Jun 10, 2024 | Administrative |
Addendum 1: Final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 9, 2024 | Nov 21, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Sep 11, 2024 | Sep 23, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 16, 2024 | Sep 16, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 20, 2024 | Sep 20, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 23, 2024 | Sep 23, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 4, 2024 | Nov 21, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 21, 2024 | Nov 21, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 21, 2024 | Dec 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Jan 15, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Nov 21, 2024 | Jan 11, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2024 | Dec 20, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2024 | Nov 27, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2024 | Dec 5, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 21, 2024 | Apr 25, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Dec 19, 2024 | Dec 19, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2025 | Jan 9, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 16, 2025 | Jan 16, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 10, 2025 | Mar 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 10, 2025 | Mar 13, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 10, 2025 | Mar 12, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2025 | Mar 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2025 | Mar 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 10, 2025 | Mar 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 21, 2025 | Mar 21, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 7, 2025 | Apr 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2025 | Apr 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2025 | Apr 11, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 10, 2025 | Apr 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2025 | Apr 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2025 | Apr 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2025 | Apr 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 25, 2025 | May 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $85,000
| Name | Role | License on permit |
|---|---|---|
| Erik Stanton Chan Lun Chan Associates | Architect | C24663 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019