168 Hancock St
San Francisco permit 202210265263 · Castro/Upper Market
Ground flr: replace foundation @ front & non property line side of garage. replace (e) garage door. center opening from entry walkway to front yard. 2nd flr: replace windows & flooring, (n) balcony @ front yard. reroofing. (n) skylight. raise parapet. (n) trim & stocco. dry rot repairs.
- Filed
- Oct 26, 2022
- Issued
- Jul 31, 2023 (9 months after filing)
- Completed
- Jan 10, 2025 (17 months after issuance)
- Review stops
- 21 stops across 3 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 26, 2022 | Oct 31, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 31, 2022 | Jul 20, 2023 | — |
Zoning review Planning · CP-ZOC | Nov 1, 2022 | Mar 31, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 12, 2023 | Jul 18, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 12, 2023 | May 31, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 12, 2023 | Apr 12, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 18, 2023 | Jul 18, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 20, 2023 | Jul 31, 2023 | Administrative |
Addendum 1: Arch mep final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 7, 2023 | Sep 7, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 7, 2023 | Oct 2, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 7, 2023 | Oct 4, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 7, 2023 | Sep 15, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 7, 2023 | Mar 14, 2024 | — |
Building plan review Building Inspection · BLDG | Oct 17, 2023 | Oct 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2023 | Nov 13, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 17, 2023 | Feb 5, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2023 | Nov 15, 2023 | Approved |
Building plan review Building Inspection · BLDG | Feb 9, 2024 | Feb 14, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 9, 2024 | Mar 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2024 | Feb 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 14, 2024 | Apr 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $49,000
| Name | Role | License on permit |
|---|---|---|
| Sandra L Chan | Architect | C27326 |
| Paul Chan Pctc Engineering | Engineer | C59840 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025