86 Sussex St
San Francisco permit 202210275297 · Glen Park
To erect a 1-story, 1 adu unit, type vn building, r-3, new adu on the rear yard of existing front building, under state program #65852.2.
- Filed
- Oct 27, 2022
- Issued
- Mar 21, 2024 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 60 stops across 6 departments
- Comments issued
- 11 times, by Public Works, Fire Department, Public Utilities, Building Inspection, Permit Center
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 27, 2022 | Nov 21, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 21, 2022 | Oct 31, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2022 | Nov 16, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 21, 2022 | Jun 7, 2023 | — |
Urban forestry Public Works · DPW-BUF | Nov 21, 2022 | Dec 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2022 | Dec 12, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2022 | Dec 12, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 21, 2022 | Feb 22, 2024 | — |
Fire prevention review Fire Department · SFFD | Nov 2, 2023 | Dec 7, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 2, 2023 | Nov 2, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 2, 2023 | Dec 14, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 13, 2023 | Nov 27, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 16, 2023 | Dec 11, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2023 | Dec 12, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 13, 2023 | Dec 13, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 13, 2023 | Dec 14, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 13, 2023 | Dec 15, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2023 | Dec 19, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 13, 2023 | Dec 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2023 | Dec 18, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 8, 2024 | Jan 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 8, 2024 | Jan 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 8, 2024 | Jan 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2024 | Jan 9, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 8, 2024 | Jan 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 8, 2024 | Jan 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2024 | Jan 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 10, 2024 | Jan 10, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Feb 14, 2024 | Feb 20, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 22, 2024 | Mar 21, 2024 | Administrative |
Addendum 1: Final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 17, 2024 | Apr 23, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 18, 2024 | Apr 18, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2024 | May 7, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Apr 22, 2024 | Apr 22, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 24, 2024 | Apr 24, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 29, 2024 | May 6, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 6, 2024 | May 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 7, 2024 | May 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2024 | May 13, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 7, 2024 | May 20, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 7, 2024 | May 14, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2024 | May 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 7, 2024 | Jun 12, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 7, 2024 | Sep 17, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 18, 2024 | Jul 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 18, 2024 | Aug 8, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jul 18, 2024 | Sep 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 18, 2024 | Jul 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 18, 2024 | Aug 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 18, 2024 | Jul 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 16, 2024 | Aug 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 16, 2024 | Aug 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 16, 2024 | Aug 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 16, 2024 | Aug 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2024 | Sep 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2024 | Sep 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2024 | Sep 10, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2024 | Sep 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 9, 2024 | Sep 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2024 | Sep 23, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Ernest Hartley Selander Selander Architects | Architect | C12715 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022