2808 Vallejo St
San Francisco permit 202210285369 · Pacific Heights
Expansion of previously permitted deck
- Filed
- Oct 28, 2022
- Issued
- Jun 23, 2023 (8 months after filing)
- Completed
- Dec 11, 2024 (18 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 20 stops across 3 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 28, 2022 | Nov 3, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 3, 2022 | Jan 5, 2023 | — |
Permit Processing Center Building Inspection · PPC | Nov 3, 2022 | Mar 1, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Dec 14, 2022 | Dec 14, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 5, 2023 | Feb 24, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 24, 2023 | Feb 24, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 24, 2023 | Feb 28, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 1, 2023 | Jun 23, 2023 | — |
Addendum 1: Arch.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 22, 2024 | Sep 5, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Aug 23, 2024 | Oct 2, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 28, 2024 | Aug 28, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 29, 2024 | Aug 29, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 5, 2024 | Sep 5, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Sep 13, 2024 | Sep 26, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 26, 2024 | Sep 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 2, 2024 | Nov 2, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 2, 2024 | Dec 4, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 25, 2024 | Nov 25, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 25, 2024 | Dec 5, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 2, 2024 | Dec 3, 2024 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $11,751
| Name | Role | License on permit |
|---|---|---|
| Robert M Edmonds Edmonds & Lee Architects | Architect | C30208 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2015