2808 Vallejo St

San Francisco permit 202210285369 · Pacific Heights

Deck, stairs or patio coverFull plan reviewComplete
Street view · Jan 2015
Google Street View of 2808 Vallejo St, Jan 2015
Scope of work
As written on the permit application.

Expansion of previously permitted deck

Timeline
Key dates from the city record.
Filed
Oct 28, 2022
Issued
Jun 23, 2023 (8 months after filing)
Completed
Dec 11, 2024 (18 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
20 stops across 3 departments
Comments issued
3 times, by Permit Center, Building Inspection
Put on hold
Once

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 3, 2022—

Zoning review

Planning · CP-ZOC

Jan 5, 2023—

Permit Processing Center

Building Inspection · PPC

Mar 1, 2023—

Planning neighborhood notice

Planning · CP-NP

Dec 14, 2022—

Building plan review

Building Inspection · BLDG

Feb 24, 2023—

Building plan review

Building Inspection · BLDG

Feb 24, 2023—

Zoning review

Planning · CP-ZOC

Feb 28, 2023—

Central Permit Bureau

Building Inspection · CPB

Jun 23, 2023—

Addendum 1: Arch.

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Sep 5, 2024Issued Comments

Central Permit Bureau

Building Inspection · CPB

Oct 2, 2024Administrative

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 28, 2024Not Applicable

Electrical pre-screening

Building Inspection · PRE-MECH-E

Aug 29, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Sep 5, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Sep 26, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 26, 2024Approved

Building plan review

Building Inspection · BLDG

Nov 2, 2024Issued Comments

Permit Processing Center

Building Inspection · PPC

Dec 4, 2024Administrative

Building plan review

Building Inspection · BLDG

Nov 25, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Dec 5, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 3, 2024Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$11,751
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Robert M Edmonds

Edmonds & Lee Architects

ArchitectC30208
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202210285369 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record