CheckMyDesigner

2333 Buchanan St

San Francisco permit 202210285388 · Pacific Heights

Commercial or tenant improvementFull plan reviewComplete
Street view · Jun 2016
Google Street View of 2333 Buchanan St, Jun 2016
Scope of work
As written on the permit application.

Remodel of existing linear accelerator and control room.replace of existing linear accelelatro equipment.staff toilet room upgrade. this is an osphd 3 bldg.

Timeline
Key dates from the city record.
Filed
Oct 28, 2022
Issued
Apr 12, 2023 (5 months after filing)
Completed
Dec 10, 2024 (20 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
14 stops across 3 departments
Comments issued
Not recorded for this permit
Put on hold
3 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 31, 2022—

Building plan review

Building Inspection · BLDG

Jan 17, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Feb 10, 2023—

Fire prevention review

Fire Department · SFFD

Nov 17, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 20, 2023—

Permit Processing Center

Building Inspection · PPC

Apr 3, 2023—

Electrical plan review

Building Inspection · MECH-E

Mar 15, 2023—

Structural plan approval

Building Inspection · PAD-STR

Mar 27, 2023—

Building plan review

Building Inspection · BLDG

Feb 13, 2023—

Building plan review

Building Inspection · BLDG

Mar 28, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Mar 29, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 28, 2023—

Fire prevention review

Fire Department · SFFD

Apr 3, 2023—

Central Permit Bureau

Building Inspection · CPB

Apr 12, 2023—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$1,949,365
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Anna R KempfArchitectC39256
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202210285388 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record