4245 23rd St
San Francisco permit 202210285454 · Noe Valley
Interior renovation of(e)garage level laundry room & storage room,1st level kitchen & living room,2nd level hall bath & bedrooms.exterior rear addition to add a bedroom on the garage level,enlarge the 2nd level.scope of work also includes(n)interior stair to(n)roof deck.
- Filed
- Oct 28, 2022
- Issued
- Jun 14, 2024 (20 months after filing)
- Completed
- Aug 24, 2026 (26 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 28, 2022 | Nov 17, 2022 | Administrative |
Zoning review Planning · CP-ZOC | Nov 17, 2022 | Sep 27, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 17, 2022 | Jun 4, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jun 23, 2023 | Jul 26, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 28, 2023 | Oct 20, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 28, 2023 | Oct 26, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 28, 2023 | Oct 26, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2023 | Sep 30, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2023 | Oct 11, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 27, 2023 | Jan 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2023 | Dec 11, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 26, 2024 | Mar 5, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 26, 2024 | Mar 7, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 26, 2024 | Mar 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 26, 2024 | Feb 28, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 26, 2024 | Jun 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 26, 2024 | Mar 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 26, 2024 | Feb 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 8, 2024 | May 9, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 8, 2024 | May 9, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2024 | May 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2024 | May 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2024 | May 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2024 | Jun 14, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Meagan Leigh Holmes Min+ Architecture | Architect | C-35929 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025