1939 Market St
San Francisco permit 202211045959 · Mission
Erect a 15 story bldg with 187 dwelling units, residential/commercial(warmshell) ,type 1a. 100% affordable housing
- Filed
- Nov 4, 2022
- Issued
- Oct 13, 2023 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 73 stops across 9 departments
- Comments issued
- 16 times, by Fire Department, Public Utilities, Building Inspection, Permit Center, Public Works
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 4, 2022 | Nov 4, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 4, 2022 | May 31, 2023 | — |
Permit Processing Center Building Inspection · PPC | Nov 4, 2022 | Sep 26, 2023 | Administrative |
CON CON-BOND | Feb 13, 2023 | Jul 20, 2023 | — |
Disability access review Mayor's Office on Disability · MOD | Feb 13, 2023 | Aug 9, 2023 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2023 | Mar 20, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 13, 2023 | Jun 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 13, 2023 | May 18, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2023 | Feb 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2023 | May 4, 2023 | — |
Public health review Public Health · HEALTH | Feb 13, 2023 | Feb 13, 2023 | — |
Public Health HEALTH-MH | Feb 13, 2023 | May 23, 2023 | — |
Public Health HEALTH-HM | Feb 13, 2023 | Feb 14, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 22, 2023 | Jun 14, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2023 | May 24, 2023 | — |
Public Health HEALTH-HM | May 22, 2023 | Jun 12, 2023 | — |
Development fee collection Building Inspection · DFCU | Jun 21, 2023 | Jun 21, 2023 | — |
Public Health HEALTH-MH | Aug 4, 2023 | Aug 10, 2023 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Aug 4, 2023 | Sep 20, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 4, 2023 | Aug 9, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 4, 2023 | Aug 11, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 4, 2023 | Sep 15, 2023 | Approved-Stipulated |
Public Health HEALTH-HM | Aug 4, 2023 | Aug 7, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 10, 2023 | Aug 15, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2023 | Sep 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 22, 2023 | Sep 26, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 26, 2023 | Oct 3, 2023 | Administrative |
Addendum 2: Deep foundations/ foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 19, 2024 | Sep 26, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 23, 2024 | Sep 23, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 25, 2024 | Sep 25, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 26, 2024 | Sep 26, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Sep 27, 2024 | Sep 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Nov 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2024 | Sep 27, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 27, 2024 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 19, 2024 | Sep 26, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 23, 2024 | Sep 23, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 25, 2024 | Sep 25, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 26, 2024 | Sep 26, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Sep 27, 2024 | Sep 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Nov 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2024 | Sep 27, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 27, 2024 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 5: Architecture
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 9, 2024 | Oct 23, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 17, 2024 | Oct 17, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 18, 2024 | Oct 18, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 21, 2024 | Oct 21, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 24, 2024 | Nov 5, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Nov 1, 2024 | Nov 1, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 1, 2024 | Nov 1, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 4, 2024 | Nov 4, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Nov 5, 2024 | Nov 5, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 5, 2024 | Nov 5, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 5, 2024 | Nov 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 6, 2024 | Nov 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 6, 2024 | Nov 15, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2024 | Nov 19, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 6, 2024 | Nov 14, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 6, 2024 | Nov 7, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2024 | Nov 12, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 6, 2024 | Feb 5, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 6, 2024 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2025 | Sep 15, 2025 | Issued Comments |
Address verification Building Inspection · ADDR | Apr 24, 2026 | Apr 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $86,686,000
| Name | Role | License on permit |
|---|---|---|
| Paulett Long Taggart Paulett Taggart Architects | Architect | C10957 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026