354 Molimo Dr
San Francisco permit 202211045960 · West of Twin Peaks
1/f new conditioned space including new stairs, 1 bathroom, & new deck. 2/f horizontal addition (lightwell infill), kitchen remodel & new powder room. 3/f bathroom remodel w/ new skylight. result in 2 bedrooms, 2.5 bathroom, family room, & office on 1/f. no changes to street facade.
- Filed
- Nov 4, 2022
- Issued
- Feb 3, 2025 (27 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 43 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Public Utilities
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 4, 2022 | Nov 14, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 15, 2022 | Jul 25, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | May 3, 2023 | May 18, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 25, 2023 | Aug 24, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2023 | Aug 25, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2023 | Sep 22, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2023 | Sep 22, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2024 | Oct 4, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 4, 2024 | Dec 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 4, 2024 | Oct 25, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 4, 2024 | Oct 17, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 4, 2024 | Oct 9, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 4, 2024 | Dec 18, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Oct 25, 2024 | Nov 7, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Oct 25, 2024 | Nov 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 12, 2024 | Nov 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2024 | Nov 15, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2024 | Nov 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 25, 2024 | Nov 26, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 25, 2024 | Dec 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 25, 2024 | Nov 26, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 25, 2024 | Dec 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2024 | Feb 3, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 3, 2025 | Feb 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 20, 2025 | Feb 24, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 24, 2025 | Apr 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 24, 2025 | Mar 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2025 | Apr 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 24, 2025 | Mar 18, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2025 | Mar 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2025 | Feb 26, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 24, 2025 | Jun 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 7, 2025 | May 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 7, 2025 | May 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2025 | May 30, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2025 | May 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 7, 2025 | May 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 2, 2025 | Jun 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 2, 2025 | Jun 2, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2025 | Jun 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 2, 2025 | Jun 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 9, 2025 | Jun 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 18, 2025 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $360,208
| Name | Role | License on permit |
|---|---|---|
| Matthew H Hollis Mh Architects | Architect | C-28252 |
| Jason Allen Pisano Hom-Pisano Engineering Inc | Engineer | C69708 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2017