4483 Mission St
San Francisco permit 202211075998 · Excelsior
One story horizontal addition with new mezzanine on 1st floor for change of use to limited restaurant.
- Filed
- Nov 7, 2022
- Issued
- Jan 18, 2024 (14 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 59 stops across 7 departments
- Comments issued
- 15 times, by Fire Department, Building Inspection, Public Utilities, Permit Center, Public Works, Public Health
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 7, 2022 | Nov 15, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 16, 2022 | Mar 7, 2023 | — |
Permit Processing Center Building Inspection · PPC | Nov 16, 2022 | Jan 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 8, 2023 | Jun 1, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 8, 2023 | Mar 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 8, 2023 | Apr 3, 2023 | — |
Public health review Public Health · HEALTH | Mar 8, 2023 | Mar 14, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 13, 2023 | May 15, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Mar 28, 2023 | Jun 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 6, 2023 | Jun 6, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 6, 2023 | Sep 15, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 6, 2023 | Jun 15, 2023 | — |
Public health review Public Health · HEALTH | Jun 6, 2023 | Jun 6, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 19, 2023 | Sep 26, 2023 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Sep 26, 2023 | Jan 18, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 2, 2023 | Nov 6, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 20, 2023 | Nov 20, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 20, 2023 | Dec 1, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 20, 2023 | Dec 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2023 | Dec 21, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2023 | Dec 1, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 7, 2023 | Dec 7, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 14, 2023 | Dec 14, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 18, 2023 | Dec 18, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 18, 2023 | Dec 18, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 19, 2023 | Dec 19, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2023 | Dec 26, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Dec 22, 2023 | Dec 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2024 | Jan 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2024 | Jan 12, 2024 | Approved-Stipulated |
Addendum 1: Final - structural, architectural.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 22, 2024 | Jan 29, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 23, 2024 | Jan 23, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jan 25, 2024 | Jan 25, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jan 31, 2024 | Feb 9, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 8, 2024 | Feb 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 12, 2024 | Feb 12, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 12, 2024 | Apr 15, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 12, 2024 | Apr 4, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2024 | Apr 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 12, 2024 | Apr 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2024 | Feb 28, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 12, 2024 | Feb 13, 2024 | Approved |
Public health review Public Health · HEALTH | Feb 12, 2024 | Mar 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 12, 2024 | Oct 4, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Mar 14, 2024 | Mar 14, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 30, 2024 | May 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 6, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 25, 2024 | Jun 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Jul 11, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 16, 2024 | Jul 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 23, 2024 | Jul 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2024 | Sep 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 13, 2024 | Sep 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 13, 2024 | Sep 16, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 13, 2024 | Oct 3, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2024 | Sep 13, 2024 | Approved |
Public health review Public Health · HEALTH | Sep 13, 2024 | Sep 13, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Sep 18, 2024 | Sep 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2024 | Oct 23, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $485,565
| Name | Role | License on permit |
|---|---|---|
| Charles C Chan Cc Architects Inc | Architect | C31716 |
| Edmond Wong Ekw Engineering | Engineer | C86522 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025