2270 Mckinnon Av
San Francisco permit 202211076023 · Bayview Hunters Point
To erect a 5-story, type iiib & ia building. occupancy class b, s-1, f-1, s-2.
- Filed
- Nov 7, 2022
- Issued
- Sep 9, 2024 (22 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 130 stops across 7 departments
- Comments issued
- 25 times, by Planning, Fire Department, Building Inspection, Permit Center, Public Works, Public Utilities
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Nov 7, 2022 | Nov 7, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2022 | Nov 14, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 14, 2022 | Aug 30, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 14, 2022 | Mar 8, 2024 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2022 | Mar 20, 2023 | — |
Fire prevention review Fire Department · SFFD | Nov 18, 2022 | May 16, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2022 | Jan 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2022 | Aug 8, 2023 | Approved |
Public health review Public Health · HEALTH | Nov 18, 2022 | Jan 29, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | May 10, 2023 | Feb 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 16, 2023 | Sep 18, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 25, 2023 | Oct 6, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 29, 2023 | Dec 29, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jan 4, 2024 | Jan 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2024 | Jan 25, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 21, 2024 | Mar 1, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Feb 29, 2024 | Feb 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 1, 2024 | Mar 6, 2024 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Mar 1, 2024 | Mar 1, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 8, 2024 | Sep 9, 2024 | Administrative |
Addendum 1: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 10, 2024 | Sep 19, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 19, 2024 | Sep 19, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Sep 19, 2024 | Sep 19, 2024 | Administrative |
Public health review Public Health · HEALTH | Sep 19, 2024 | Oct 7, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 19, 2024 | Oct 23, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Oct 8, 2024 | Oct 8, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 23, 2024 | Sep 24, 2025 | Administrative |
Addendum 2: Foundation grading & pile design
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 10, 2024 | Sep 20, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 19, 2024 | Sep 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2024 | Sep 20, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Sep 20, 2024 | Nov 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 20, 2024 | Sep 23, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 20, 2024 | Jul 31, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 2, 2025 | May 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 2, 2025 | May 5, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 11, 2025 | Jul 11, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2025 | Sep 24, 2025 | Administrative |
Addendum 3: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 17, 2024 | Oct 2, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 2, 2024 | Oct 2, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2024 | Oct 3, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Oct 3, 2024 | Dec 13, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 3, 2024 | Oct 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 3, 2024 | Aug 20, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 5, 2025 | Mar 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 12, 2025 | Mar 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2025 | Sep 24, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Aug 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2025 | Aug 20, 2025 | Approved |
Addendum 4: Architectural / mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 22, 2025 | Nov 7, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 13, 2025 | Nov 24, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 9, 2025 | Dec 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2025 | Dec 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Dec 23, 2025 | Jan 13, 2026 | Approved |
Building plan review Building Inspection · BLDG | Dec 23, 2025 | Jan 30, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2025 | Jan 21, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 23, 2025 | Feb 18, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 23, 2025 | Feb 12, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2025 | Dec 29, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 23, 2025 | Jan 23, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2025 | Dec 26, 2025 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Dec 23, 2025 | Dec 29, 2025 | Approved |
Plumbing plan check Building Inspection · PID-PC | Dec 23, 2025 | Feb 10, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 23, 2025 | Jul 1, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jan 28, 2026 | Jan 28, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2026 | Apr 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 16, 2026 | Apr 30, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2026 | May 5, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 5, 2026 | May 14, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 7, 2026 | May 14, 2026 | Issued Comments |
Plumbing plan check Building Inspection · PID-PC | May 7, 2026 | May 7, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | May 8, 2026 | May 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 18, 2026 | May 18, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 19, 2026 | May 19, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 10, 2026 | Jun 10, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 11, 2026 | Jun 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 11, 2026 | Jun 15, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 11, 2026 | Jun 11, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 11, 2026 | Jun 12, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2026 | Jun 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 11, 2026 | Jun 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2026 | Jun 15, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jun 11, 2026 | Jun 22, 2026 | Approved |
Plumbing plan check Building Inspection · PID-PC | Jun 11, 2026 | Jun 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2026 | Jul 13, 2026 | Administrative |
Addendum 5: Self-storage interior fit out
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 14, 2026 | Aug 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 6, 2026 | Aug 6, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 7, 2026 | Aug 31, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 7, 2026 | Aug 28, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Aug 7, 2026 | Aug 13, 2026 | Not Applicable |
Public Health HEALTH-MH | Aug 7, 2026 | Aug 11, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Aug 7, 2026 | Oct 20, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Sep 2, 2026 | Sep 2, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Oct 16, 2026 | Oct 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2026 | Oct 27, 2026 | Administrative |
Addendum 6: Fire sprinkler
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 22, 2026 | Apr 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2026 | Apr 29, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 29, 2026 | May 7, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 29, 2026 | Jul 16, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 29, 2026 | Jul 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 16, 2026 | Jul 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 16, 2026 | Jul 17, 2026 | Administrative |
Addendum 7: Fire alarm & elevator emergency comm system (2-way)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 17, 2026 | Aug 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 6, 2026 | Aug 6, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 6, 2026 | Aug 13, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 6, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Oct 5, 2026 | Oct 5, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 8: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 22, 2026 | Apr 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 1, 2026 | May 1, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 1, 2026 | May 28, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 1, 2026 | Jun 1, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | May 1, 2026 | Jul 6, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 1, 2026 | Jul 6, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 30, 2026 | Jun 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 6, 2026 | Jul 9, 2026 | Administrative |
Addendum 9: Errcs (if required)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 8, 2026 | Sep 17, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2026 | Sep 17, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 17, 2026 | Sep 25, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 17, 2026 | Oct 6, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 6, 2026 | Oct 15, 2026 | Administrative |
Addendum 10: Rev to issued s3
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 3, 2026 | Jun 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 24, 2026 | Jun 24, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 24, 2026 | Aug 3, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 24, 2026 | Aug 3, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 24, 2026 | Jul 8, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 24, 2026 | Sep 25, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 25, 2026 | Sep 25, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 25, 2026 | Sep 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 25, 2026 | Oct 6, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $23,145,072
| Name | Role | License on permit |
|---|---|---|
| Brian H Liles Jackson Liles Architecture | Architect | C27249 |
| Blake Dilsworth Kpff | Engineer | s3929 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026