1923 Pierce St
San Francisco permit 202211096146 · Pacific Heights
Foundation replacement: replace all extg brick foundation with concrete structure. build out basement level with mud room, media room and bathroom. upstairs: install new header at kitchen to backyard doorway, reconfigure garage level secondary egress through side yard.
- Filed
- Nov 9, 2022
- Issued
- Nov 9, 2023 (12 months after filing)
- Completed
- Oct 17, 2024 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Public Works
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 9, 2022 | Nov 9, 2022 | — |
Intake Building Inspection · INTAKE | Nov 16, 2022 | Nov 16, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 16, 2022 | Nov 16, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 16, 2022 | Nov 16, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Nov 23, 2022 | Nov 23, 2022 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 23, 2022 | Jan 25, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 25, 2023 | May 4, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 25, 2023 | May 4, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 22, 2023 | Mar 22, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 7, 2023 | Aug 8, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 25, 2023 | May 4, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 4, 2023 | Jun 15, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 11, 2023 | Jul 11, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 1, 2023 | Aug 3, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2023 | Aug 9, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2023 | Aug 11, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2023 | Aug 23, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 1, 2023 | Oct 3, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 1, 2023 | Sep 1, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 3, 2023 | Oct 5, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 6, 2023 | Oct 18, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 18, 2023 | Oct 24, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 25, 2023 | Oct 25, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 25, 2023 | Nov 9, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $375,000
| Name | Role | License on permit |
|---|---|---|
| Bradford Charles Tardy Bradford C. Tardy Architect | Architect | C24623 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2015