San Francisco permit 202211096146 · Pacific Heights

Seismic retrofit or foundationFull plan reviewComplete
Street view · Nov 2015
Google Street View of 1923 Pierce St, Nov 2015
Scope of work
As written on the permit application.

Foundation replacement: replace all extg brick foundation with concrete structure. build out basement level with mud room, media room and bathroom. upstairs: install new header at kitchen to backyard doorway, reconfigure garage level secondary egress through side yard.

Timeline
Key dates from the city record.
Filed
Nov 9, 2022
Issued
Nov 9, 2023 (12 months after filing)
Completed
Oct 17, 2024 (11 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 5 departments
Comments issued
4 times, by Building Inspection, Public Works
Put on hold
4 times
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Nov 9, 2022—

Intake

Building Inspection · INTAKE

Nov 16, 2022—

Zoning review

Planning · CP-ZOC

Nov 16, 2022—

Building plan review

Building Inspection · BLDG

Nov 16, 2022—

Permit Center

Permit Center · PERMIT-CTR

Nov 23, 2022Administrative

Central Permit Bureau

Building Inspection · CPB

Jan 25, 2023—

Structural plan approval

Building Inspection · PAD-STR

May 4, 2023—

Building plan review

Building Inspection · BLDG

May 4, 2023—

Central Permit Bureau

Building Inspection · CPB

Mar 22, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Aug 8, 2023—

Building plan review

Building Inspection · BLDG

May 4, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 15, 2023—

Building plan review

Building Inspection · BLDG

Jul 11, 2023—

Building plan review

Building Inspection · BLDG

Aug 3, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 9, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 11, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 23, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 3, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 1, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 5, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 18, 2023Approved

Zoning review

Planning · CP-ZOC

Oct 24, 2023Approved

Permit Processing Center

Building Inspection · PPC

Oct 25, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Nov 9, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$375,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Bradford Charles Tardy

Bradford C. Tardy Architect

ArchitectC24623
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202211096146 on the city's permit tracking site