CheckMyDesigner

1618 Quesada Av

San Francisco permit 202211106257 · Bayview Hunters Point

AdditionFull plan reviewIssued
Street view · Mar 2025
Google Street View of 1618 Quesada Av, Mar 2025
Scope of work
As written on the permit application.

One-story rear buiding addition. interior bedroom remodel. deck addition over (e) garage lightwell.

Timeline
Key dates from the city record.
Filed
Nov 10, 2022
Issued
Apr 15, 2025 (29 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 6 departments
Comments issued
8 times, by Building Inspection, Fire Department, Public Works
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 10, 2022—

Zoning review

Planning · CP-ZOC

Apr 23, 2024Approved

Planning neighborhood notice

Planning · CP-NP

Feb 8, 2024Administrative

Permit Center

Permit Center · PERMIT-CTR

Mar 26, 2024Administrative

Building plan review

Building Inspection · BLDG

Jun 13, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 14, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 15, 2024Approved

Fire prevention review

Fire Department · SFFD

Aug 21, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 23, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 26, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 6, 2024Approved

Building plan review

Building Inspection · BLDG

Oct 8, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 8, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Dec 3, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Dec 17, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 17, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Dec 20, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 30, 2024Approved

Fire prevention review

Fire Department · SFFD

Jan 10, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 5, 2025Approved

Fire prevention review

Fire Department · SFFD

Feb 5, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 7, 2025Approved

Zoning review

Planning · CP-ZOC

Feb 13, 2025Approved

Permit Processing Center

Building Inspection · PPC

Feb 27, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 15, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$100,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jaime Pasion Arafiles

Jaime Pasion Arafiles

EngineerC40483
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202211106257 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record