555 Pine St
San Francisco permit 202211106284 · Financial District/South Beach
Install 540 gal urea tank on the 1st floor of 555 pine. provide & install fuel piping & associated fuel pumps at 555 pine which transfer between the two buildings. provide & install piping for the equipment mentioned above. all misc. arch, mech, elec, & controls work required to complete the project
- Filed
- Nov 10, 2022
- Issued
- Nov 19, 2025 (36 months after filing)
- Completed
- Not completed yet
- Review stops
- 43 stops across 5 departments
- Comments issued
- 11 times, by Building Inspection, Planning, Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 10, 2022 | Nov 10, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 28, 2022 | Nov 28, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 28, 2022 | Nov 28, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Nov 28, 2022 | Nov 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 28, 2022 | Nov 28, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Nov 28, 2022 | Nov 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 29, 2022 | Dec 1, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 1, 2022 | Jan 31, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 1, 2022 | Oct 2, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jan 31, 2023 | Mar 1, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Jan 31, 2023 | Jan 31, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 2, 2024 | May 13, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 14, 2024 | May 28, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 14, 2024 | May 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 14, 2024 | Aug 14, 2024 | — |
Zoning review Planning · CP-ZOC | May 14, 2024 | Jun 25, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2024 | Jun 11, 2024 | Approved |
Public health review Public Health · HEALTH | May 14, 2024 | May 14, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jun 28, 2024 | Jun 28, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 26, 2024 | Nov 26, 2024 | Approved |
Public health review Public Health · HEALTH | Nov 26, 2024 | Nov 26, 2024 | Approved-Stipulated |
Electrical plan review Building Inspection · MECH-E | Nov 27, 2024 | Nov 27, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 2, 2024 | Dec 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 9, 2024 | Dec 9, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 20, 2024 | Dec 20, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 23, 2024 | Dec 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2024 | Dec 23, 2024 | Approved |
Public health review Public Health · HEALTH | Dec 23, 2024 | Dec 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 30, 2024 | Dec 30, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 29, 2025 | Jan 29, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 29, 2025 | Jan 29, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 29, 2025 | Jan 29, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 3, 2025 | Feb 3, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Feb 3, 2025 | Mar 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 3, 2025 | Feb 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2025 | Sep 9, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 9, 2025 | Sep 11, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2025 | Oct 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 9, 2025 | Sep 10, 2025 | Approved |
Public health review Public Health · HEALTH | Sep 9, 2025 | Sep 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2025 | Sep 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 23, 2025 | Sep 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2025 | Nov 19, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Gary Michael Semling Stantec Architecture Inc. | Architect | C21541 |
| Thomas Craig Ewert Complete Project Solutions | Engineer | S3931 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026