2200 Keith St
San Francisco permit 202211106343 · Bayview Hunters Point
Tenant improvement to (e) office/warehouse by building a 2nd level to the open warehouse area, w/ new stair going to the new 2nd fl office/storage area. maintain 15ft from 1st fl finish level to ceiling as required. no exterior work. all foundation/functional work only pertaining to the interior.
- Filed
- Nov 10, 2022
- Issued
- May 8, 2025 (30 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 6 times, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Nov 10, 2022 | Nov 10, 2022 | — |
Intake Building Inspection · INTAKE | Nov 10, 2022 | Nov 10, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 12, 2022 | Mar 23, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 23, 2023 | Mar 23, 2023 | — |
Intake Building Inspection · INTAKE | May 15, 2023 | May 15, 2023 | Administrative |
Zoning review Planning · CP-ZOC | May 16, 2023 | Jul 3, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jul 5, 2023 | Jul 5, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Aug 24, 2023 | Aug 24, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 29, 2023 | Sep 13, 2023 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Aug 30, 2023 | Aug 30, 2023 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 13, 2023 | Sep 13, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 15, 2023 | Oct 27, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 19, 2024 | Mar 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 16, 2024 | May 22, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 9, 2024 | Jul 19, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 1, 2024 | Aug 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 10, 2024 | Sep 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2024 | Sep 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 24, 2024 | Oct 7, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 7, 2024 | Nov 25, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 27, 2024 | Nov 27, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 27, 2024 | May 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Yao Kun Chen Yao Chen Architecture Studio | Architect | C36094 |
| Doug Lee Doug Lee | Engineer | C74001 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025