CheckMyDesigner

615 Alvarado St

San Francisco permit 202211146435 · Noe Valley

AdditionFull plan reviewIssued
Street view · May 2025
Google Street View of 615 Alvarado St, May 2025
Scope of work
As written on the permit application.

Minor reconfiguration & expansion of 1st flr. horizontal addition of artist studio, deck & spiral stair in the back yard. renovation of 2nd flr bathroom. enclosure of open-air entryway. replacement of various windows.

Timeline
Key dates from the city record.
Filed
Nov 14, 2022
Issued
May 21, 2024 (18 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 4 departments
Comments issued
6 times, by Building Inspection, Public Utilities
Put on hold
Twice
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 15, 2022—

Permit Processing Center

Building Inspection · PPC

Feb 12, 2024—

Zoning review

Planning · CP-ZOC

Aug 28, 2023Approved

Planning neighborhood notice

Planning · CP-NP

Jul 13, 2023—

Building plan review

Building Inspection · BLDG

Oct 19, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 16, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 6, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 31, 2023Approved

Building pre-screening

Building Inspection · PRE-BLDG

Sep 22, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 13, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 6, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Nov 8, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jan 12, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 17, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 17, 2023Approved

Building plan review

Building Inspection · BLDG

Jan 8, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 6, 2023Approved

Zoning review

Planning · CP-ZOC

Dec 6, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 8, 2023Approved

Building plan review

Building Inspection · BLDG

Jan 19, 2024Approved

Zoning review

Planning · CP-ZOC

Jan 25, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 19, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Feb 7, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 25, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 21, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$213,868
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Gyo Max Obata

Obata Noblin Office

ArchitectC38332
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202211146435 on the city's permit tracking site