1652 Sunnydale Av
San Francisco permit 202211146447 · Visitacion Valley
Mayor dir 17-02 priority project - erect a 4-story, type 5a/type 1a, apartment building with 95 units and one basement level.
- Filed
- Nov 14, 2022
- Issued
- Aug 12, 2024 (21 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 200 stops across 7 departments
- Comments issued
- 61 times, by Planning, Building Inspection, Fire Department, Public Works, Mayor's Office on Disability, Permit Center
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 14, 2022 | Nov 15, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 15, 2022 | Dec 14, 2022 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 15, 2022 | Feb 8, 2024 | — |
Disability access review Mayor's Office on Disability · MOD | Mar 23, 2023 | Apr 10, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 23, 2023 | Apr 13, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 23, 2023 | Sep 5, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 23, 2023 | May 1, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 23, 2023 | Sep 1, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 1, 2023 | Sep 12, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 1, 2023 | Sep 21, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2023 | Sep 1, 2023 | Approved |
Disability access review Mayor's Office on Disability · MOD | Oct 2, 2023 | Oct 2, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 11, 2023 | Oct 11, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 20, 2023 | Jan 8, 2024 | Issued Comments |
Disability access review Mayor's Office on Disability · MOD | Dec 20, 2023 | Dec 27, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 20, 2023 | Dec 21, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 20, 2023 | Jan 3, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2023 | Jan 31, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2023 | Dec 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Feb 2, 2024 | Feb 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 2, 2024 | Feb 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2024 | Feb 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2024 | Feb 7, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2024 | Feb 2, 2024 | Approved |
Disability access review Mayor's Office on Disability · MOD | Feb 5, 2024 | Feb 5, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Feb 8, 2024 | Feb 8, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 8, 2024 | Aug 12, 2024 | Administrative |
Addendum 1: Foundation, podium & superstructure.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 30, 2024 | Sep 27, 2024 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Sep 3, 2024 | Sep 16, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Sep 10, 2024 | Sep 10, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 11, 2024 | Sep 11, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 12, 2024 | Sep 12, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 16, 2024 | Sep 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Nov 5, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2024 | Oct 3, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Sep 27, 2024 | May 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Dec 27, 2024 | Jan 3, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 27, 2024 | Dec 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 12, 2025 | Mar 14, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 23, 2025 | Apr 28, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 12, 2025 | May 13, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 13, 2025 | Jun 18, 2025 | Administrative |
Addendum 2: Shoring.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 20, 2025 | Mar 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2025 | Mar 7, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 10, 2025 | Mar 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2025 | Mar 18, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 10, 2025 | Mar 24, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 24, 2025 | Jun 12, 2025 | Administrative |
Addendum 3: Architecture, landscape & mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 19, 2024 | Oct 4, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 23, 2024 | Sep 23, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 25, 2024 | Sep 25, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 26, 2024 | Sep 26, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 30, 2024 | Sep 30, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 1, 2024 | Oct 1, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 4, 2024 | Oct 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 8, 2024 | Oct 8, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 8, 2024 | Oct 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 8, 2024 | Oct 25, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 8, 2024 | Oct 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 8, 2024 | Oct 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 8, 2024 | Oct 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 8, 2024 | Oct 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 8, 2024 | Oct 29, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 8, 2024 | Jul 7, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Dec 24, 2024 | Dec 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 31, 2024 | Jan 2, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 31, 2024 | Dec 31, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 3, 2025 | Jan 3, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 7, 2025 | Jan 7, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 5, 2025 | Mar 6, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 5, 2025 | Mar 5, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 6, 2025 | Mar 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 7, 2025 | Mar 7, 2025 | Issued Comments |
Plumbing plan check Building Inspection · PID-PC | Mar 10, 2025 | Mar 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 12, 2025 | Mar 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2025 | Mar 18, 2025 | Approved-Stipulated |
Plumbing plan check Building Inspection · PID-PC | Apr 1, 2025 | Jun 5, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 29, 2025 | Apr 29, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 9, 2025 | May 19, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 15, 2025 | May 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 19, 2025 | May 19, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 21, 2025 | May 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 5, 2025 | Jun 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2025 | Jun 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2025 | Jun 6, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 5, 2025 | Jun 5, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 10, 2025 | Jun 10, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 10, 2025 | Jun 10, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 10, 2025 | Jul 1, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2025 | Jul 16, 2025 | Administrative |
Addendum 4: Fire protection / fire sprinkler.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 25, 2025 | Oct 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2025 | Oct 14, 2025 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Oct 14, 2025 | Oct 16, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 14, 2025 | Jul 16, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Mar 2, 2026 | Mar 2, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Apr 2, 2026 | Apr 20, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 16, 2026 | Jun 25, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 16, 2026 | Jul 16, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 16, 2026 | Aug 25, 2026 | Administrative |
Addendum 5: Fire alarm two-way communication, emergency voice / alarm communication system.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 3, 2026 | Mar 12, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2026 | Mar 13, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Mar 13, 2026 | Apr 20, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 13, 2026 | Oct 30, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Aug 14, 2026 | Aug 31, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Oct 29, 2026 | Oct 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2026 | In progress | In Progress |
Addendum 6: Solar pv / battery.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 5, 2026 | Feb 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2026 | Feb 25, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 25, 2026 | Mar 16, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2026 | Mar 16, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 25, 2026 | Mar 3, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Feb 25, 2026 | Mar 13, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 25, 2026 | Aug 24, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 7, 2026 | May 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 7, 2026 | May 13, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 7, 2026 | May 8, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | May 7, 2026 | May 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 26, 2026 | Jun 22, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 26, 2026 | Jun 22, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 26, 2026 | May 27, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 26, 2026 | Jul 1, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 21, 2026 | Jul 21, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 7, 2026 | Aug 7, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 7, 2026 | Aug 7, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 7, 2026 | Aug 20, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 7, 2026 | Aug 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 24, 2026 | Sep 15, 2026 | Administrative |
Addendum 7: Metal stairs.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 21, 2025 | Nov 3, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 3, 2025 | Nov 3, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 3, 2025 | Dec 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2025 | Dec 5, 2025 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Nov 3, 2025 | Nov 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2025 | Nov 6, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 3, 2025 | Mar 3, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 30, 2026 | Feb 18, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Feb 12, 2026 | Feb 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 12, 2026 | Feb 17, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2026 | Apr 6, 2026 | Administrative |
Addendum 8: Errcs.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 18, 2026 | Mar 3, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2026 | Mar 4, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 4, 2026 | Mar 19, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Mar 4, 2026 | Mar 23, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 4, 2026 | Jun 17, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | May 27, 2026 | May 27, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jun 15, 2026 | Jun 15, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2026 | Jun 22, 2026 | Administrative |
Addendum 10: Exterior building maintenance.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 20, 2026 | May 11, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 12, 2026 | May 12, 2026 | Administrative |
Building plan review Building Inspection · BLDG | May 12, 2026 | Jul 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 12, 2026 | Jul 2, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | May 12, 2026 | May 18, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 12, 2026 | May 13, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 12, 2026 | Sep 1, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 24, 2026 | Aug 26, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 24, 2026 | Aug 27, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2026 | Aug 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 1, 2026 | Oct 14, 2026 | Administrative |
Addendum 11: Curtain wall & storefront.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 24, 2026 | Sep 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2026 | Oct 2, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Oct 2, 2026 | Nov 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2026 | Nov 2, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Oct 2, 2026 | Oct 29, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2026 | Oct 7, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Oct 2, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 12: Rev 1 to addendum 3 (arch, landscape, mep)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 26, 2025 | Dec 15, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jan 15, 2026 | Jan 30, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2026 | Feb 2, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 2, 2026 | Mar 4, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 2, 2026 | Feb 10, 2026 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 2, 2026 | Feb 12, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Feb 2, 2026 | Feb 12, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 2, 2026 | Feb 4, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 2, 2026 | Mar 9, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2026 | Feb 6, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Feb 2, 2026 | Feb 12, 2026 | Approved |
Plumbing plan check Building Inspection · PID-PC | Feb 2, 2026 | Feb 24, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 2, 2026 | Jun 2, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Mar 2, 2026 | Mar 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 24, 2026 | Mar 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 25, 2026 | Apr 6, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 25, 2026 | Mar 30, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Mar 25, 2026 | Mar 30, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2026 | Apr 10, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 25, 2026 | Apr 21, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2026 | Mar 27, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Mar 25, 2026 | Mar 25, 2026 | Approved |
Plumbing plan check Building Inspection · PID-PC | Apr 8, 2026 | Apr 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2026 | May 12, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | May 7, 2026 | May 7, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2026 | May 8, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | May 8, 2026 | May 8, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2026 | May 21, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 21, 2026 | May 28, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 21, 2026 | May 21, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 21, 2026 | May 21, 2026 | Approved |
Plumbing plan check Building Inspection · PID-PC | May 21, 2026 | May 28, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 29, 2026 | May 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2026 | Jun 10, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $69,971,776
| Name | Role | License on permit |
|---|---|---|
| Karen E Murray Van Meter Williams Pollack Llp | Architect | C-27052 |
| Bryan G Cortnik American Subsurface Engineer | Engineer | S-5136 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022