CheckMyDesigner

4627 17th St

San Francisco permit 202211146484 · Inner Sunset

AdditionFull plan reviewIssued
Street view · Jun 2016
Google Street View of 4627 17th St, Jun 2016
Scope of work
As written on the permit application.

Remodel of existing house with one-story vertical addition; total interior remodel with selective removal of interior elements; lowering a portion of the existing basement.

Timeline
Key dates from the city record.
Filed
Nov 14, 2022
Issued
Mar 8, 2024 (16 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
42 stops across 6 departments
Comments issued
9 times, by Building Inspection, Public Utilities

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 23, 2022—

Zoning review

Planning · CP-ZOC

Dec 4, 2023Approved

Permit Processing Center

Building Inspection · PPC

Feb 20, 2024Administrative

Building plan review

Building Inspection · BLDG

Dec 28, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 11, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Dec 19, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Jan 8, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 9, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jan 11, 2024Approved

Building plan review

Building Inspection · BLDG

Jan 30, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Feb 2, 2024Approved-Stipulated

Fire prevention review

Fire Department · SFFD

Feb 12, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Mar 8, 2024Administrative

Addendum 1: Arch mep final

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 22, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Apr 15, 2024Approved

Electrical pre-screening

Building Inspection · PRE-MECH-E

Apr 15, 2024Not Applicable

Mechanical pre-screening

Building Inspection · PRE-MECH

Apr 19, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 22, 2024Administrative

Building plan review

Building Inspection · BLDG

Jun 18, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

May 7, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

May 8, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Apr 25, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 25, 2024Approved

Permit Processing Center

Building Inspection · PPC

Aug 27, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jun 18, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 13, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 14, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 20, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 25, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 9, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 26, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 15, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 7, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 8, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 12, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 20, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Aug 27, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 26, 2024Approved

Fire prevention review

Fire Department · SFFD

Aug 22, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Aug 26, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 26, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Oct 24, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$920,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Geddes J Ulinskas

Geddes Ulinskas Architects

ArchitectC27862
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202211146484 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record