CheckMyDesigner

89 Belgrave Av

San Francisco permit 202211156492 · Inner Sunset

New buildingFull plan reviewComplete
Street view · May 2025
Google Street View of 89 Belgrave Av, May 2025
Scope of work
As written on the permit application.

To erect a 2-story, type vb, 1-unit adu structure at rear.

Timeline
Key dates from the city record.
Filed
Nov 15, 2022
Issued
Aug 17, 2023 (9 months after filing)
Completed
Nov 21, 2024 (15 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 5 departments
Comments issued
None
Put on hold
10 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 17, 2022—

Zoning review

Planning · CP-ZOC

Mar 2, 2023—

Building plan review

Building Inspection · BLDG

Mar 24, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Apr 4, 2023—

Fire prevention review

Fire Department · SFFD

Apr 12, 2023—

Urban forestry

Public Works · DPW-BUF

Jul 7, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Mar 2, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 11, 2023—

Permit Processing Center

Building Inspection · PPC

Jul 6, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 2, 2023—

Building plan review

Building Inspection · BLDG

Apr 25, 2023—

Zoning review

Planning · CP-ZOC

Mar 27, 2023—

Mechanical and energy plan review

Building Inspection · MECH

May 23, 2023—

Fire prevention review

Fire Department · SFFD

May 12, 2023—

Building plan review

Building Inspection · BLDG

May 22, 2023—

Building plan review

Building Inspection · BLDG

May 22, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 2, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 7, 2023—

Zoning review

Planning · CP-ZOC

Jun 8, 2023—

Fire prevention review

Fire Department · SFFD

Jun 8, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 8, 2023—

Urban forestry

Public Works · DPW-BUF

Jun 27, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 9, 2023—

Development fee collection

Building Inspection · DFCU

Jun 28, 2023—

Urban forestry

Public Works · DPW-BUF

Jul 8, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Aug 17, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Complete
Estimated cost
$375,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Cameron Helland

Helland Architecture

ArchitectC35654
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202211156492 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record