89 Belgrave Av
San Francisco permit 202211156492 · Inner Sunset
To erect a 2-story, type vb, 1-unit adu structure at rear.
- Filed
- Nov 15, 2022
- Issued
- Aug 17, 2023 (9 months after filing)
- Completed
- Nov 21, 2024 (15 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 26 stops across 5 departments
- Comments issued
- None
- Put on hold
- 10 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 15, 2022 | Nov 17, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 18, 2022 | Mar 2, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2022 | Mar 24, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2022 | Apr 4, 2023 | — |
Fire prevention review Fire Department · SFFD | Nov 18, 2022 | Apr 12, 2023 | — |
Urban forestry Public Works · DPW-BUF | Nov 18, 2022 | Jul 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2022 | Mar 2, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2022 | Jan 11, 2023 | — |
Permit Processing Center Building Inspection · PPC | Nov 18, 2022 | Jul 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2023 | Mar 2, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 24, 2023 | Apr 25, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 27, 2023 | Mar 27, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 4, 2023 | May 23, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 12, 2023 | May 12, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 25, 2023 | May 22, 2023 | — |
Building plan review Building Inspection · BLDG | May 22, 2023 | May 22, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2023 | Jun 2, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 2, 2023 | Jun 7, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 8, 2023 | Jun 8, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 8, 2023 | Jun 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 8, 2023 | Jun 8, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 8, 2023 | Jun 27, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 8, 2023 | Jun 9, 2023 | — |
Development fee collection Building Inspection · DFCU | Jun 28, 2023 | Jun 28, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 29, 2023 | Jul 8, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 6, 2023 | Aug 17, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $375,000
| Name | Role | License on permit |
|---|---|---|
| Cameron Helland Helland Architecture | Architect | C35654 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025