3223 Folsom St
San Francisco permit 202211156582 · Bernal Heights
Commencment of work under pa201708215412 for a soft story original permit granted in 2017. we are now ready to begin work and the original permit needs to be looked at again to comply with nov#202045653.
- Filed
- Nov 15, 2022
- Issued
- May 27, 2025 (30 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 11 stops across 4 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Nov 15, 2022 | Nov 15, 2022 | — |
Intake Building Inspection · INTAKE | Nov 15, 2022 | Nov 15, 2022 | — |
Code enforcement Building Inspection · CES | Nov 15, 2022 | Nov 15, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 15, 2022 | Nov 15, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Nov 16, 2022 | Nov 16, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2022 | Dec 1, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 1, 2022 | Apr 7, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 1, 2022 | Jan 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 24, 2023 | Mar 22, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 7, 2023 | Apr 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 7, 2023 | May 27, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $102,000
| Name | Role | License on permit |
|---|---|---|
| John Taylor Hood Hood Thomas Architects | Architect | C14187 |
| Daniel Barringer Barringer Design | Engineer | C68258 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025