San Francisco permit 202211166654 · Marina

Addition (type unconfirmed)Full plan reviewIssued
Street view · Jan 2025
Google Street View of 3255 Octavia St, Jan 2025
Scope of work
As written on the permit application.

3/f: kitchen/bathroom renovation, combine (2)bedroom into (1)bedroom, 2/f: kitchen/bathroom renovation; ground level: widen garage door, new sliding door to backyard. horizontal addition of 17 sf at front of garage.

Timeline
Key dates from the city record.
Filed
Nov 7, 2024
Issued
Jul 23, 2025 (8 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
31 stops across 6 departments
Comments issued
8 times, by Permit Center, Building Inspection, Public Works, Fire Department
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Nov 16, 2022—

Zoning review

Planning · CP-ZOC

Feb 17, 2023—

Intake

Building Inspection · INTAKE

Jan 17, 2023—

Intake

Building Inspection · INTAKE

Feb 1, 2023—

Intake

Building Inspection · INTAKE

Jul 1, 2024Administrative

Permit Center

Permit Center · PERMIT-CTR

Jul 31, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Jul 25, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Jul 29, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jul 29, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Nov 1, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 24, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Oct 31, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Nov 7, 2024Administrative

Zoning review

Planning · CP-ZOC

Nov 8, 2024Approved

Building plan review

Building Inspection · BLDG

Jan 10, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 22, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 13, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Nov 18, 2024Approved

Permit Processing Center

Building Inspection · PPC

May 6, 2025Administrative

Fire prevention review

Fire Department · SFFD

Jan 15, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Mar 26, 2025Approved

Building plan review

Building Inspection · BLDG

Apr 22, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 10, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 31, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 3, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

May 1, 2025Approved

Fire prevention review

Fire Department · SFFD

Apr 22, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Apr 28, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 24, 2025Approved

Zoning review

Planning · CP-ZOC

Apr 21, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jul 23, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$420,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jerome Douglas Tobias

Arcflux Studio

PayorC34070
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202211166654 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record