20 Hernandez Av
San Francisco permit 202211176759 · West of Twin Peaks
Replace (e) 2-story wood deck & stair w/ (n) 2-story wood deck & stair. replace (e) roofed canopy @ 2nd floor ext. door w/ (n) canopy across rear facade. infill (e) north ext. door @ 1st floor garage. 4) replace (e) rear window @ 1st floor garage w/ (n) ext. door from garage to deck. relocate (e)
- Filed
- Nov 17, 2022
- Issued
- Jul 10, 2023 (8 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 15 stops across 2 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 17, 2022 | Nov 18, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 18, 2022 | Mar 30, 2023 | — |
Permit Processing Center Building Inspection · PPC | Nov 18, 2022 | Jun 13, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Feb 8, 2023 | Mar 30, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 30, 2023 | Jun 8, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 8, 2023 | Jun 12, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2023 | Jul 10, 2023 | — |
Addendum 1: Final - arch,mech, t24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 14, 2023 | Aug 14, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 28, 2023 | Sep 28, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2023 | Sep 19, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 28, 2023 | Dec 26, 2023 | In Progress |
Building plan review Building Inspection · BLDG | Dec 6, 2023 | Dec 19, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 6, 2023 | Dec 15, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2023 | Dec 21, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 26, 2023 | Jul 24, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $46,221
| Name | Role | License on permit |
|---|---|---|
| Eric Harry Hartz Gast Architecture | Architect | C-33994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025