21 Santos St
San Francisco permit 202211186887
Bldg 37f: demolition of 2-story, type v, residential bldg.
- Filed
- Nov 18, 2022
- Issued
- Apr 5, 2023 (5 months after filing)
- Completed
- May 30, 2024 (14 months after issuance)
- Review stops
- 8 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 18, 2022 | Dec 6, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 6, 2022 | Mar 15, 2023 | — |
Zoning review Planning · CP-ZOC | Dec 8, 2022 | Dec 27, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2022 | Jan 17, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 30, 2022 | Jan 31, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 6, 2023 | Jan 9, 2023 | — |
Public health review Public Health · HEALTH | Jan 6, 2023 | Mar 15, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 15, 2023 | Apr 5, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Demolitions
- Status
- Complete
- Estimated cost
- $222,032
| Name | Role | License on permit |
|---|---|---|
| Ryan Jay Beaton Kpff | Engineer | 82786 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2023