Mayoral ed-17-02 for 'mazzola garden' public open space on bart parcel (3505/034) per the 1629 market dev. agreement. scope includes: 1) concrete masonry unit enclosure w/gate to surround (e) bart vent structure 2) tensile fabric canopy within enclosure 3) new paving 4) new planting areas 5) k4 rate

Timeline
Key dates from the city record.
Filed
Nov 21, 2022
Issued
Jun 14, 2023 (7 months after filing)
Completed
Mar 28, 2024 (9 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
18 stops across 4 departments
Comments issued
Not recorded for this permit
Put on hold
4 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 28, 2022—

Zoning review

Planning · CP-ZOC

Jan 19, 2023—

Permit Processing Center

Building Inspection · PPC

Jun 9, 2023—

Building plan review

Building Inspection · BLDG

Apr 14, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jan 18, 2023—

Electrical plan review

Building Inspection · MECH-E

Mar 29, 2023—

Street use and mapping

Public Works · DPW-BSM

Dec 21, 2022—

Fire prevention review

Fire Department · SFFD

Mar 29, 2023—

Structural plan approval

Building Inspection · PAD-STR

Jun 1, 2023—

Building plan review

Building Inspection · BLDG

Apr 14, 2023—

Fire prevention review

Fire Department · SFFD

Mar 29, 2023—

Zoning review

Planning · CP-ZOC

Jun 8, 2023—

Building plan review

Building Inspection · BLDG

Jun 7, 2023—

Electrical plan review

Building Inspection · MECH-E

Jun 6, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 8, 2023—

Fire prevention review

Fire Department · SFFD

Jun 8, 2023—

Building plan review

Building Inspection · BLDG

Jun 7, 2023—

Central Permit Bureau

Building Inspection · CPB

Jun 14, 2023—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$200,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jeff Brink

Dci+Dse Engineers

EngineerS-6142
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202211216918 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record