50 Colton St
San Francisco permit 202211216918 · Mission
Mayoral ed-17-02 for 'mazzola garden' public open space on bart parcel (3505/034) per the 1629 market dev. agreement. scope includes: 1) concrete masonry unit enclosure w/gate to surround (e) bart vent structure 2) tensile fabric canopy within enclosure 3) new paving 4) new planting areas 5) k4 rate
- Filed
- Nov 21, 2022
- Issued
- Jun 14, 2023 (7 months after filing)
- Completed
- Mar 28, 2024 (9 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 21, 2022 | Nov 28, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 28, 2022 | Jan 19, 2023 | — |
Permit Processing Center Building Inspection · PPC | Nov 28, 2022 | Jun 9, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 5, 2022 | Apr 14, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2022 | Jan 18, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Dec 5, 2022 | Mar 29, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2022 | Dec 21, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 5, 2022 | Mar 29, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 12, 2023 | Jun 1, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 29, 2023 | Apr 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 29, 2023 | Mar 29, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 1, 2023 | Jun 8, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 1, 2023 | Jun 7, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 1, 2023 | Jun 6, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 1, 2023 | Jun 8, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 1, 2023 | Jun 8, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 7, 2023 | Jun 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 9, 2023 | Jun 14, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Jeff Brink Dci+Dse Engineers | Engineer | S-6142 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025