3675 Clay St
San Francisco permit 202211227078 · Presidio Heights
Horizontal addition. renovation on all floors.
- Filed
- Nov 22, 2022
- Issued
- Aug 31, 2023 (9 months after filing)
- Completed
- Oct 15, 2026 (37 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 17 stops across 5 departments
- Comments issued
- None
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 22, 2022 | Dec 5, 2022 | — |
Building inspector Building Inspection · BID-INSP | Nov 23, 2022 | Nov 23, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 5, 2022 | Apr 14, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 5, 2022 | Aug 24, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Feb 23, 2023 | Apr 12, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 25, 2023 | Jul 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 25, 2023 | Jul 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 25, 2023 | May 3, 2023 | — |
Urban forestry Public Works · DPW-BUF | Apr 25, 2023 | Jul 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 25, 2023 | May 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2023 | Jul 7, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 13, 2023 | Jul 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 13, 2023 | Aug 18, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 18, 2023 | Aug 23, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2023 | Aug 21, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 18, 2023 | Aug 21, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 24, 2023 | Aug 31, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,475,000
| Name | Role | License on permit |
|---|---|---|
| John Patrick Maniscalco John Maniscalco Architecture | Architect | C25148 |
| Jason R Powers Zfa Structural Engineers | Engineer | 76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023