3621 Clay St
San Francisco permit 202211287189 · Presidio Heights
Main sfr building - interior: excavation at level 1 to 9'6", wall reconfigurations, (n) kitchen, baths, electrical, lighting and radiant heating system. exterior: add 12' wide garage door. (n) dormer. gable roof, deck at level 2 & 4. (n) siding, wood clad windows, doors.(n) roof, colums & entry door
- Filed
- Nov 28, 2022
- Issued
- Sep 22, 2023 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 23 stops across 4 departments
- Comments issued
- None
- Put on hold
- 7 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 28, 2022 | Nov 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 28, 2022 | Aug 7, 2023 | — |
Zoning review Planning · CP-ZOC | Nov 29, 2022 | Jul 17, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 29, 2022 | Apr 5, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 29, 2022 | Mar 15, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 29, 2022 | Mar 31, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 29, 2022 | Jul 19, 2023 | — |
Urban forestry Public Works · DPW-BUF | Nov 29, 2022 | Jan 3, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 29, 2022 | Dec 6, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 15, 2023 | Mar 15, 2023 | — |
Planning neighborhood notice Planning · CP-NP | May 16, 2023 | May 18, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 20, 2023 | Jun 26, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 29, 2023 | Jul 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 20, 2023 | Jul 26, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 20, 2023 | Jul 31, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 20, 2023 | Aug 1, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 20, 2023 | Jul 21, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2023 | Jul 27, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 20, 2023 | Jul 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 20, 2023 | Jul 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 31, 2023 | Aug 2, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2023 | Jul 31, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 7, 2023 | Sep 22, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $2,767,750
| Name | Role | License on permit |
|---|---|---|
| Jeffrey O Graham Graham Architects | Architect | C22806 |
| Diarmuid Hugo Mac Neill Dolmen Structural Engineer | Designer | C56739 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020