CheckMyDesigner

257 Justin Dr

San Francisco permit 202211287192 · Bernal Heights

Legalize or fix a violationFull plan reviewIssued
Street view · Feb 2022
Google Street View of 257 Justin Dr, Feb 2022
Scope of work
As written on the permit application.

Comply w/ nov #202298553: rebuild (e) rear deck. add 1 bar sink on 1/f. infill in-ground pool. repair front stairs. repair & relocate staircase w/ structural support. add family rm, 2 bathroom on 1/f <1000 sqft. flatwork repair in driveway area within front yard setback.

Timeline
Key dates from the city record.
Filed
Nov 28, 2022
Issued
Jan 3, 2024 (13 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 5 departments
Comments issued
7 times, by Building Inspection, Fire Department
Put on hold
3 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 23, 2022—

Building inspector

Building Inspection · BID-INSP

Dec 22, 2022—

Electrical inspector

Building Inspection · EID-INSP

Dec 22, 2022—

Zoning review

Planning · CP-ZOC

May 17, 2023—

Permit Processing Center

Building Inspection · PPC

Dec 23, 2023Administrative

Building plan review

Building Inspection · BLDG

Sep 5, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jun 26, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 6, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 13, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Oct 11, 2023—

Fire prevention review

Fire Department · SFFD

Nov 7, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 16, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 16, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 10, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Nov 15, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Nov 8, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 5, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Dec 7, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 5, 2023Approved

Fire prevention review

Fire Department · SFFD

Dec 7, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Dec 20, 2023—

Zoning review

Planning · CP-ZOC

Dec 22, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 13, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Jan 3, 2024Administrative

Building inspector

Building Inspection · BID-INSP

Dec 27, 2023—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$350,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Norman Jerry ScheelEngineerS-2567
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202211287192 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record