257 Justin Dr
San Francisco permit 202211287192 · Bernal Heights
Comply w/ nov #202298553: rebuild (e) rear deck. add 1 bar sink on 1/f. infill in-ground pool. repair front stairs. repair & relocate staircase w/ structural support. add family rm, 2 bathroom on 1/f <1000 sqft. flatwork repair in driveway area within front yard setback.
- Filed
- Nov 28, 2022
- Issued
- Jan 3, 2024 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 21, 2022 | Dec 23, 2022 | — |
Building inspector Building Inspection · BID-INSP | Dec 22, 2022 | Dec 22, 2022 | — |
Electrical inspector Building Inspection · EID-INSP | Dec 22, 2022 | Dec 22, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 23, 2022 | May 17, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 23, 2022 | Dec 23, 2023 | Administrative |
Building plan review Building Inspection · BLDG | May 17, 2023 | Sep 5, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 17, 2023 | Jun 26, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 17, 2023 | Jun 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 17, 2023 | Jun 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 26, 2023 | Oct 11, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 26, 2023 | Nov 7, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2023 | Oct 16, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 16, 2023 | Oct 16, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2023 | Nov 10, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 7, 2023 | Nov 15, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 8, 2023 | Nov 8, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 29, 2023 | Dec 5, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 4, 2023 | Dec 7, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2023 | Dec 5, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 6, 2023 | Dec 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 7, 2023 | Dec 20, 2023 | — |
Zoning review Planning · CP-ZOC | Dec 7, 2023 | Dec 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 8, 2023 | Dec 13, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 26, 2023 | Jan 3, 2024 | Administrative |
Building inspector Building Inspection · BID-INSP | Dec 27, 2023 | Dec 27, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Norman Jerry Scheel | Engineer | S-2567 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022