2710 Divisadero St
San Francisco permit 202211287248 · Pacific Heights
Addition of new elevator
- Filed
- Nov 28, 2022
- Issued
- Nov 16, 2023 (12 months after filing)
- Completed
- Aug 15, 2024 (9 months after issuance)
- Review stops
- 20 stops across 3 departments
- Comments issued
- Twice, by Building Inspection, Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 28, 2022 | Nov 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 17, 2023 | Feb 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 23, 2023 | Nov 15, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Feb 27, 2023 | May 3, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | May 4, 2023 | Jul 31, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jul 31, 2023 | Aug 24, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 31, 2023 | Sep 13, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 9, 2023 | Aug 14, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 15, 2023 | Sep 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 15, 2023 | Sep 18, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2023 | Sep 15, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2023 | Nov 16, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 27, 2023 | Nov 1, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 7, 2023 | Nov 13, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 7, 2023 | Nov 8, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2023 | Nov 13, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2023 | Nov 7, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 10, 2023 | Nov 13, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 10, 2023 | Nov 13, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 13, 2023 | Nov 15, 2023 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Dan William Phipps Dan Phipps Architects | Architect | C15366 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025