278 28th Av
San Francisco permit 202211297266 · Seacliff
Build a 3 story rear addition,kitchen interior remodel and master bathroom remodel.
- Filed
- Nov 29, 2022
- Issued
- Mar 14, 2024 (15 months after filing)
- Completed
- Jun 12, 2025 (15 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 16 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 29, 2022 | Feb 22, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 22, 2023 | Nov 30, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 22, 2023 | Mar 6, 2024 | — |
Planning neighborhood notice Planning · CP-NP | Sep 13, 2023 | Oct 4, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 5, 2023 | Jan 31, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2023 | Dec 28, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2023 | Dec 9, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2023 | Dec 12, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 21, 2023 | Dec 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 16, 2024 | Jan 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 23, 2024 | Feb 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 23, 2024 | Mar 5, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 23, 2024 | Feb 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2024 | Mar 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2024 | Feb 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 6, 2024 | Mar 14, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $700,000
| Name | Role | License on permit |
|---|---|---|
| Jaime Pasion Arafiles Jaime Pasion Arafiles | Architect | C40483 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022