CheckMyDesigner

555 Post St

San Francisco permit 202211307418 · Tenderloin

OtherFull plan reviewIssued
Street view · Jan 2025
Google Street View of 555 Post St, Jan 2025
Scope of work
As written on the permit application.

Priority process - exterior repairs/deferred maintenance in compliance w/facade/inspection ord. remove brick to determine condition of embedded steel. repair/waterproofing of (e) embedded steel elements. replace corroded steel w/in wall. r/r brick as needed. repointing of brick mortar joints.

Timeline
Key dates from the city record.
Filed
Nov 30, 2022
Issued
Oct 8, 2026 (46 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
9 stops across 4 departments
Comments issued
None
Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

Nov 30, 2022—

Intake

Building Inspection · INTAKE

Nov 30, 2022—

Central Permit Bureau

Building Inspection · CPB

Dec 15, 2022—

Zoning review

Planning · CP-ZOC

Feb 14, 2023—

Building plan review

Building Inspection · BLDG

Mar 27, 2023—

Fire prevention review

Fire Department · SFFD

May 2, 2023—

Street use and mapping

Public Works · DPW-BSM

May 5, 2023—

Permit Processing Center

Building Inspection · PPC

May 8, 2023—

Central Permit Bureau

Building Inspection · CPB

Oct 8, 2026Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$165,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Vahid Sattary

Sattart Structural Engineer

Engineer3973
Sources