65 A Henry St
San Francisco permit 202211307424 · Castro/Upper Market
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa#202010166621:new furnace location under stiars, new 12x24" fixed glazing at master shower (tempered, enclosure of a 60 sf deck (no reduction of useable outdoor space). removal of window at upstairs lounge, nw exterior wall to enclose the deck aligned to the prop.line, new 72" gas
- Filed
- Nov 30, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 5 stops across 2 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 30, 2022 | Nov 30, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 2, 2022 | Dec 2, 2022 | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Withdrawn
- Estimated cost
- $12,000
| Name | Role | License on permit |
|---|---|---|
| Mark A Cruz | Architect | C36564 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026