1501 Sunnydale Av
San Francisco permit 202212017477 · Visitacion Valley
Block 3a/lot 3: ti of g/f commercial space for use as an early care and education (ece) center.ti. consists of interior non-structural partitions, finishes & exterior courtyard improvements; mep, fp, lv will be design-build & submitted under seperate permits; (base permit # 202106031523)
- Filed
- Dec 1, 2022
- Issued
- Oct 24, 2025 (35 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 22 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Dec 1, 2022 | Dec 1, 2022 | — |
Intake Building Inspection · INTAKE | Dec 1, 2022 | Dec 1, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 1, 2022 | Dec 1, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 6, 2022 | Apr 19, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 19, 2023 | Jul 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 14, 2023 | Jul 27, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jul 13, 2023 | Jul 21, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 27, 2023 | Aug 8, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 8, 2023 | Aug 30, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 30, 2023 | Aug 31, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2023 | Oct 13, 2023 | Approved |
Public health review Public Health · HEALTH | Oct 13, 2023 | Oct 13, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Mar 4, 2025 | Mar 20, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 5, 2025 | May 20, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 17, 2025 | Jun 23, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 17, 2025 | Jun 26, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 17, 2025 | Sep 2, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 24, 2025 | Jun 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 26, 2025 | Jun 26, 2025 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2025 | Aug 25, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2025 | Aug 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 2, 2025 | Oct 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,440,851
| Name | Role | License on permit |
|---|---|---|
| Marsha Ann Maytum Leddy Maytum Stacy Archi | Architect | C12450 |
| Ryan Joshua Jang Leddy Maytum Architects | Architect | C33368 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025