451 10th Av
San Francisco permit 202212057634 · Inner Richmond
Remodel(e)2/f unit interior spaces,adding a(n)bath,extend a(n)22 sf bay window @ rear yard side to make a bedroom suite.expand(e) 2/f unit vertically to (e)g/f interior to create a 2 story unit.remodel(e)g/fspaces to include a (n)master bedroom & bath.
- Filed
- Dec 5, 2022
- Issued
- Aug 26, 2024 (21 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 42 stops across 6 departments
- Comments issued
- 12 times, by Building Inspection, Public Works, Fire Department
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 5, 2022 | Dec 15, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 15, 2022 | Nov 21, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 15, 2022 | May 31, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Sep 14, 2023 | Sep 28, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 22, 2023 | Jan 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 22, 2023 | Nov 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2023 | Dec 14, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 31, 2024 | Feb 9, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 14, 2024 | Feb 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 14, 2024 | Feb 14, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 14, 2024 | Mar 6, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2024 | Feb 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 16, 2024 | Feb 16, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 13, 2024 | May 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 13, 2024 | May 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 13, 2024 | May 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 31, 2024 | Aug 26, 2024 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 13, 2025 | Jun 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 15, 2025 | Jul 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 15, 2025 | May 18, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 15, 2025 | Sep 2, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 15, 2025 | Sep 2, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2025 | Aug 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 15, 2025 | Jul 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2025 | Jul 16, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2025 | Jul 15, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 15, 2025 | Jun 16, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Dec 9, 2025 | Dec 10, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 9, 2025 | Dec 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 9, 2025 | Dec 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 15, 2026 | Jan 15, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 18, 2026 | Mar 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 18, 2026 | Mar 23, 2026 | Not Applicable |
Fire prevention review Fire Department · SFFD | Mar 30, 2026 | Apr 9, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 9, 2026 | Apr 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 22, 2026 | Apr 27, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | May 11, 2026 | May 11, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2026 | May 19, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | May 15, 2026 | May 18, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2026 | May 18, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 16, 2026 | Sep 25, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $438,033
| Name | Role | License on permit |
|---|---|---|
| Winnie Hing-Wan Tam Winnie Tam | Architect | C31166 |
| Stephen Chan | Engineer | 4533 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025