100 Palo Alto Av
San Francisco permit 202212057648 · Twin Peaks
Full subgrade enclosure for battery storage in rear yard. tesla solar roof & battery storage( >20 kw/h)
- Filed
- Dec 5, 2022
- Issued
- Jul 27, 2023 (8 months after filing)
- Completed
- Jan 21, 2025 (18 months after issuance)
- Review stops
- 15 stops across 3 departments
- Comments issued
- None
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 5, 2022 | Dec 5, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 6, 2022 | Dec 6, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 6, 2022 | Dec 6, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 9, 2022 | Dec 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 19, 2022 | Dec 19, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2022 | Dec 20, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 20, 2022 | May 30, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 14, 2023 | Mar 13, 2023 | — |
Electrical plan review Building Inspection · MECH-E | May 26, 2023 | May 26, 2023 | — |
Fire prevention review Fire Department · SFFD | May 30, 2023 | Jun 29, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 30, 2023 | Jul 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 30, 2023 | Jul 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 6, 2023 | Jul 10, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 13, 2023 | Jul 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 13, 2023 | Jul 27, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Joseph Patrick Dangaran Joseph P. Dangaran | Architect | C34653 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026