CheckMyDesigner

3676 17th St

San Francisco permit 202212067705 · Castro/Upper Market

Home remodel (type unconfirmed)Full plan reviewComplete
Street view · Jan 2021
Google Street View of 3676 17th St, Jan 2021
Scope of work
As written on the permit application.

Partially excavate lower level to create (n) principal suite and laundry in (e) 1st flr storage area and connect to 2nd flr unit w/(n) stair . renovate 2nd flr kitchen and living and 3rd flr bedroom and 2nd bathrooms (n) windows balcony and spiral stair at rear of structure.

Timeline
Key dates from the city record.
Filed
Dec 6, 2022
Issued
Jan 17, 2024 (13 months after filing)
Completed
Jan 30, 2026 (24 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 6 departments
Comments issued
3 times, by Planning, Building Inspection, Public Works
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Dec 6, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Dec 6, 2022—

Zoning review

Planning · CP-ZOC

Jul 24, 2023—

Planning neighborhood notice

Planning · CP-NP

Jul 19, 2023—

Zoning review

Planning · CP-ZOC

Jul 24, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Aug 3, 2023Approved

Permit Center

Permit Center · PERMIT-CTR

Aug 3, 2023—

Central Permit Bureau

Building Inspection · CPB

Aug 11, 2023Administrative

Building plan review

Building Inspection · BLDG

Sep 18, 2023Issued Comments

Building pre-screening

Building Inspection · PRE-BLDG

Sep 1, 2023Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Sep 19, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Oct 4, 2023Approved

Building plan review

Building Inspection · BLDG

Oct 13, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 16, 2023Approved-Stipulated

Mechanical and energy plan review

Building Inspection · MECH

Oct 19, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 23, 2023Approved

Zoning review

Planning · CP-ZOC

Oct 26, 2023Approved

Fire prevention review

Fire Department · SFFD

Nov 1, 2023Approved

Permit Processing Center

Building Inspection · PPC

Nov 3, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 21, 2023Administrative

Zoning review

Planning · CP-ZOC

Jan 10, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jan 12, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Jan 17, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$325,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mark Reilly

Mark Reilly Architecture

ArchitectC-33112
Shaun Edward Moynahan

Semco Engineering Inc.

EngineerS-4605
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202212067705 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record