3676 17th St
San Francisco permit 202212067705 · Castro/Upper Market
Partially excavate lower level to create (n) principal suite and laundry in (e) 1st flr storage area and connect to 2nd flr unit w/(n) stair . renovate 2nd flr kitchen and living and 3rd flr bedroom and 2nd bathrooms (n) windows balcony and spiral stair at rear of structure.
- Filed
- Dec 6, 2022
- Issued
- Jan 17, 2024 (13 months after filing)
- Completed
- Jan 30, 2026 (24 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 23 stops across 6 departments
- Comments issued
- 3 times, by Planning, Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 6, 2022 | Dec 6, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 6, 2022 | Dec 6, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 6, 2022 | Jul 24, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jul 19, 2023 | Jul 19, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 24, 2023 | Jul 24, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 3, 2023 | Aug 3, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 3, 2023 | Aug 3, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 9, 2023 | Aug 11, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 11, 2023 | Sep 18, 2023 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 1, 2023 | Sep 1, 2023 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2023 | Sep 19, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2023 | Oct 4, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 12, 2023 | Oct 13, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 13, 2023 | Oct 16, 2023 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2023 | Oct 19, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 19, 2023 | Oct 23, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 23, 2023 | Oct 26, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 26, 2023 | Nov 1, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 1, 2023 | Nov 3, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 3, 2023 | Dec 21, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Dec 21, 2023 | Jan 10, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 11, 2024 | Jan 12, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 12, 2024 | Jan 17, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $325,000
| Name | Role | License on permit |
|---|---|---|
| Mark Reilly Mark Reilly Architecture | Architect | C-33112 |
| Shaun Edward Moynahan Semco Engineering Inc. | Engineer | S-4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2021