745 A Vienna St
San Francisco permit 202212067784 · Excelsior
Erect a detached 2-story, type vb, 1-unit adu at rear, per govt. code sec. 6585.2.(a)-(d). demolition of detached rear structure under pa# 202212067785.
- Filed
- Dec 6, 2022
- Issued
- Oct 7, 2024 (22 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 63 stops across 6 departments
- Comments issued
- 15 times, by Planning, Building Inspection, Permit Center, Fire Department
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 6, 2022 | Dec 8, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 8, 2022 | Sep 3, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 9, 2022 | Jun 8, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 9, 2022 | Apr 2, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 9, 2022 | Jul 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 9, 2022 | Dec 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2022 | Dec 15, 2022 | — |
Urban forestry Public Works · DPW-BUF | Dec 9, 2022 | Jun 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 8, 2023 | Jun 8, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 11, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 15, 2024 | May 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 17, 2024 | May 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 21, 2024 | May 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 21, 2024 | May 21, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 21, 2024 | May 30, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 21, 2024 | May 21, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2024 | Jun 5, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jul 22, 2024 | Jul 22, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Jul 25, 2024 | Jul 25, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Jul 30, 2024 | Aug 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 30, 2024 | Aug 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 30, 2024 | Aug 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 30, 2024 | Jul 31, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 30, 2024 | Aug 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 30, 2024 | Aug 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 3, 2024 | Oct 7, 2024 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 10, 2024 | Oct 23, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 17, 2024 | Oct 17, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 17, 2024 | Oct 17, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 23, 2024 | Oct 23, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 5, 2024 | Dec 19, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Dec 11, 2024 | Dec 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Dec 19, 2024 | Dec 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2024 | Dec 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 23, 2024 | Jan 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 23, 2024 | Dec 30, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 23, 2024 | Dec 30, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Dec 23, 2024 | Dec 27, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2024 | Dec 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 23, 2024 | Jan 10, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 23, 2024 | Feb 6, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 23, 2024 | Sep 18, 2025 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Jan 13, 2025 | Jan 13, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 24, 2025 | Jul 7, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 24, 2025 | Jul 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 24, 2025 | Jun 26, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 24, 2025 | Jun 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 24, 2025 | Sep 29, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 24, 2025 | Jul 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Aug 18, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2025 | Aug 19, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 8, 2025 | Aug 12, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2025 | Aug 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 8, 2025 | Aug 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 8, 2025 | Aug 12, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 10, 2025 | Sep 16, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 10, 2025 | Sep 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 10, 2025 | Sep 11, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 10, 2025 | Sep 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 10, 2025 | Sep 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Sep 10, 2025 | Sep 11, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Sep 17, 2025 | Sep 17, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 18, 2025 | Sep 29, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Van Thai Ly Van T. Ly & Associataes | Architect | C25710 |
| Emmanuel Kai Ming Pun Puns And Assoc | Engineer | S2883 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011