360 03rd St
San Francisco permit 202212077790 · South of Market
1st/flr: demolition of existing shower, toilet, non-structural partition wall, ceiling, lighting and finishes. upgrading existing restroom and shower into all gender accessible restrooms.
- Filed
- Dec 7, 2022
- Issued
- Mar 29, 2023 (4 months after filing)
- Completed
- Jul 17, 2023 (4 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 9 stops across 3 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 7, 2022 | Dec 7, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 7, 2022 | Dec 7, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 7, 2022 | Dec 7, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Dec 7, 2022 | Dec 7, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 7, 2022 | Dec 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 7, 2022 | Dec 7, 2022 | — |
Code enforcement Building Inspection · CES | Dec 7, 2022 | Dec 7, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 27, 2023 | Mar 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 29, 2023 | Mar 29, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Teresa K Emery Forge Architecture | Architect | C14087 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026