850 Turk St
San Francisco permit 202212087884 · Western Addition
Priority processing - 100% affordable housing. to erect a 8-story, 92-dwelling units, type 1a mixed-used building.
- Filed
- Dec 8, 2022
- Issued
- Dec 1, 2023 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 167 stops across 7 departments
- Comments issued
- 34 times, by Building Inspection, Permit Center, Fire Department, Public Works
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 8, 2022 | Dec 8, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 9, 2022 | Dec 13, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 9, 2022 | Oct 3, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 13, 2022 | Jan 30, 2023 | — |
Fire prevention review Fire Department · SFFD | Dec 13, 2022 | May 8, 2023 | — |
Urban forestry Public Works · DPW-BUF | Dec 13, 2022 | May 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 13, 2022 | Dec 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2022 | Jan 13, 2023 | — |
Public health review Public Health · HEALTH | Dec 13, 2022 | Dec 20, 2022 | — |
Public Health HEALTH-MH | Dec 20, 2022 | Mar 22, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2023 | Jan 30, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 10, 2023 | Apr 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 10, 2023 | Sep 20, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 20, 2023 | Sep 21, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 20, 2023 | Sep 27, 2023 | — |
Urban forestry Public Works · DPW-BUF | Sep 20, 2023 | Sep 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2023 | Sep 22, 2023 | Approved |
Public health review Public Health · HEALTH | Sep 20, 2023 | Sep 25, 2023 | Administrative |
Public Health HEALTH-MH | Sep 20, 2023 | Sep 25, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Sep 29, 2023 | Oct 2, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2023 | Dec 1, 2023 | Administrative |
Addendum 1: Dept. of public health - maher ordinance
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 14, 2024 | May 28, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 24, 2024 | May 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 28, 2024 | May 28, 2024 | Administrative |
Public health review Public Health · HEALTH | May 28, 2024 | May 30, 2024 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | May 28, 2024 | Nov 18, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 31, 2024 | May 8, 2025 | Administrative |
Public health review Public Health · HEALTH | Nov 14, 2024 | Nov 18, 2024 | Approved-Stipulated |
Addendum 2: Excavation, shoring & ground improvement
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 18, 2024 | Jan 30, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 22, 2024 | Jan 22, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Jan 23, 2024 | Jan 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 1, 2024 | Feb 1, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 1, 2024 | Feb 13, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2024 | Feb 5, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 1, 2024 | Nov 21, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 13, 2024 | Feb 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 16, 2024 | Feb 16, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 19, 2024 | May 2, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 7, 2024 | May 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 7, 2024 | May 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 14, 2024 | May 8, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 14, 2024 | Nov 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2024 | Nov 20, 2024 | Approved |
Addendum 3: Foundation/superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 25, 2024 | Feb 5, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 30, 2024 | Jan 30, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Feb 5, 2024 | Feb 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2024 | Feb 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 6, 2024 | Mar 1, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 6, 2024 | Feb 6, 2024 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2024 | Feb 6, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 6, 2024 | Nov 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 29, 2024 | May 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 17, 2024 | Aug 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Oct 7, 2024 | Oct 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 14, 2024 | Nov 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 14, 2024 | Nov 18, 2024 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2024 | Nov 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 27, 2024 | May 8, 2025 | Administrative |
Addendum 4: Architectire & mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 25, 2024 | Feb 5, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Jan 30, 2024 | Jan 30, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Feb 5, 2024 | Feb 5, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 19, 2024 | Mar 27, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 21, 2024 | Mar 21, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 21, 2024 | Mar 21, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 26, 2024 | Mar 26, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2024 | Mar 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 27, 2024 | Apr 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 27, 2024 | Apr 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 27, 2024 | Apr 22, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 27, 2024 | Mar 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2024 | Apr 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 27, 2024 | Mar 27, 2024 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Mar 27, 2024 | Dec 5, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 11, 2024 | May 2, 2024 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Apr 22, 2024 | Apr 22, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 26, 2024 | Apr 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 16, 2024 | May 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 20, 2024 | May 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2024 | Aug 6, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 17, 2024 | Jul 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 23, 2024 | Jul 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 24, 2024 | Jul 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 21, 2024 | Aug 21, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 21, 2024 | Aug 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2024 | Oct 30, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 11, 2024 | Oct 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 17, 2024 | Oct 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 21, 2024 | Oct 28, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2024 | Oct 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 14, 2024 | Nov 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 14, 2024 | Nov 20, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 14, 2024 | Nov 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 14, 2024 | Nov 19, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2024 | Nov 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2024 | Nov 19, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 14, 2024 | Nov 15, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Dec 5, 2024 | May 7, 2025 | Administrative |
Addendum 5: Landscape & stormwater
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 9, 2025 | Jan 15, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2025 | Jan 21, 2025 | Administrative |
Plumbing plan check Building Inspection · PID-PC | Jan 21, 2025 | May 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2025 | Feb 13, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 21, 2025 | Jan 31, 2025 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Jan 21, 2025 | Jul 7, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 5, 2025 | May 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 5, 2025 | Jun 24, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 30, 2025 | Jun 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2025 | Jul 24, 2025 | Administrative |
Addendum 6: Fire sprinkler system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 1, 2025 | Jul 8, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jul 9, 2025 | Jul 9, 2025 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Jul 9, 2025 | Jul 16, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 9, 2025 | Dec 23, 2025 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Nov 14, 2025 | Nov 14, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Dec 22, 2025 | Dec 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2025 | Jan 8, 2026 | Administrative |
Addendum 7: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 20, 2025 | Apr 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 7, 2025 | Apr 7, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 7, 2025 | May 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 7, 2025 | Apr 8, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2025 | Apr 10, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 7, 2025 | Sep 9, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 3, 2025 | Sep 4, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 4, 2025 | Sep 4, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2025 | Sep 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 9, 2025 | Sep 23, 2025 | Administrative |
Addendum 8: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 29, 2026 | Aug 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 3, 2026 | Aug 4, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Aug 4, 2026 | Aug 26, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 4, 2026 | In progress | — |
Permit Center Permit Center · PERMIT-CTR | Sep 17, 2026 | Sep 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 28, 2026 | Sep 28, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Sep 29, 2026 | Oct 23, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 9: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 26, 2026 | Apr 7, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 23, 2026 | Jul 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 24, 2026 | Jul 9, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 9, 2026 | Aug 14, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2026 | Aug 14, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Jul 9, 2026 | Aug 17, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 9, 2026 | In progress | In Progress |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 10: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 15, 2026 | Feb 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2026 | Feb 10, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 10, 2026 | Mar 12, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Feb 10, 2026 | Feb 26, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 10, 2026 | Jun 17, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Apr 1, 2026 | Apr 23, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | May 29, 2026 | May 29, 2026 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2026 | Jun 24, 2026 | Administrative |
Addendum 11: Exterior building maintenance system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 29, 2026 | May 15, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 23, 2026 | Jul 8, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2026 | Jul 9, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 9, 2026 | Aug 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2026 | Aug 14, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Jul 9, 2026 | Jul 10, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 9, 2026 | Jul 13, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 9, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 12: Solar pv
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 5, 2026 | Jan 21, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 22, 2026 | Jan 22, 2026 | Administrative |
Permit Processing Center Building Inspection · PPC | Jan 22, 2026 | Apr 7, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 23, 2026 | Mar 30, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 23, 2026 | Mar 6, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Jan 23, 2026 | Jan 29, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Jan 23, 2026 | Feb 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 7, 2026 | Apr 8, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $39,000,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Elias Simons David Baker Architects | Architect | C30025 |
| Jonas Heron Weber David Baker Architects | Architect | C35892 |
| Edward Charles Robison Edward C. Robinson, Pe | Engineer | C65883 |
| Kai Shing Chu Spi Consulting Engineers, Inc. | Engineer | C84827 |
| Raymond Nim | Engineer | C-90343 |
| Jordan Elling Hague Dci Engineers | Engineer | S-6509 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025