1667 A Fulton St #0
San Francisco permit 202212138159 · Lone Mountain/USF
Addition of 1 new adu. new foundation & lowered ground floor to provide head clearance for the new units. properties have no street frontage.
- Filed
- Dec 13, 2022
- Issued
- Aug 23, 2024 (20 months after filing)
- Completed
- Mar 13, 2026 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 37 stops across 6 departments
- Comments issued
- 12 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Dec 13, 2022 | Dec 13, 2022 | — |
Intake Building Inspection · INTAKE | Dec 13, 2022 | Dec 13, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2022 | Feb 8, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 13, 2022 | Jan 19, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 9, 2023 | Jan 23, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jan 24, 2024 | Feb 1, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 24, 2024 | Feb 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2024 | Apr 4, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Feb 13, 2024 | Feb 13, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 6, 2024 | Mar 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 2, 2024 | Apr 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 4, 2024 | Apr 4, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 10, 2024 | Apr 10, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 10, 2024 | Apr 16, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2024 | Apr 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 22, 2024 | Apr 26, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 26, 2024 | Apr 26, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 30, 2024 | Apr 30, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2024 | May 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2024 | May 7, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 6, 2024 | May 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 7, 2024 | May 13, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2024 | May 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 15, 2024 | May 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2024 | May 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 17, 2024 | Jun 21, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Jul 9, 2024 | Aug 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 5, 2024 | Aug 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 5, 2024 | Aug 6, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2024 | Aug 6, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 5, 2024 | Aug 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 5, 2024 | Aug 6, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2024 | Aug 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2024 | Aug 5, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 5, 2024 | Aug 7, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Aug 7, 2024 | Aug 7, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 7, 2024 | Aug 23, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $211,540
| Name | Role | License on permit |
|---|---|---|
| Javier Medina Mark Davis Design | Architect | C34033 |
| Gregory Paul Wallace Gregory Paul Wallace Struct | Engineer | S3308 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026