333 Battery St
San Francisco permit 202212138174 · Chinatown
The project scope include: level 3. renovation of (e) public restrooms, renovation of (e) restaurant and bar, (n) reception louge and coffee bar. renovation of (e) outdoor patio with (n) outdoor bar, concrete planter, trellis.
- Filed
- Dec 13, 2022
- Issued
- Feb 23, 2023 (2 months after filing)
- Completed
- Dec 14, 2023 (10 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 13, 2022 | Dec 13, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Dec 13, 2022 | Dec 13, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 27, 2023 | Jan 27, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2023 | Jan 27, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 27, 2023 | Jan 27, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 27, 2023 | Jan 27, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 7, 2023 | Feb 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 7, 2023 | Feb 7, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 7, 2023 | Feb 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 7, 2023 | Feb 7, 2023 | — |
Public health review Public Health · HEALTH | Feb 10, 2023 | Feb 10, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 15, 2023 | Feb 15, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 15, 2023 | Feb 15, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 17, 2023 | Feb 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2023 | Feb 23, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1,775,000
| Name | Role | License on permit |
|---|---|---|
| Sandra Biddulph Edci Engineers | Engineer | S4225 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026