375sf single story horizontal addition on first floor, remodel (e) kitchen, add (n) bathroom, add 340sf conditioned basement below grade.

Timeline
Key dates from the city record.
Filed
Dec 13, 2022
Issued
Dec 4, 2023 (12 months after filing)
Completed
Sep 20, 2024 (10 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
20 stops across 5 departments
Comments issued
3 times, by Building Inspection
Put on hold
Twice
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 19, 2022—

Zoning review

Planning · CP-ZOC

Jun 6, 2023—

Permit Processing Center

Building Inspection · PPC

Nov 29, 2023Administrative

Planning neighborhood notice

Planning · CP-NP

Jun 6, 2023—

Building plan review

Building Inspection · BLDG

Jul 31, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 6, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 28, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 7, 2023—

Building plan review

Building Inspection · BLDG

Oct 17, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Sep 28, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Sep 29, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 3, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 16, 2023Administrative

Mechanical and energy plan review

Building Inspection · MECH

Nov 16, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 7, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Nov 9, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Nov 13, 2023Approved

Building plan review

Building Inspection · BLDG

Nov 21, 2023Approved

Fire prevention review

Fire Department · SFFD

Nov 28, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Dec 4, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$190,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Marshall Bartz Schneider

Schneder Design Associates

ArchitectC29499
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202212138226 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record