1227 14th Av
San Francisco permit 202212138226 · Inner Sunset
375sf single story horizontal addition on first floor, remodel (e) kitchen, add (n) bathroom, add 340sf conditioned basement below grade.
- Filed
- Dec 13, 2022
- Issued
- Dec 4, 2023 (12 months after filing)
- Completed
- Sep 20, 2024 (10 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 20 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 13, 2022 | Dec 19, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 19, 2022 | Jun 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 19, 2022 | Nov 29, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Mar 21, 2023 | Jun 6, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 6, 2023 | Jul 31, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 6, 2023 | Oct 6, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 6, 2023 | Jun 28, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 6, 2023 | Jun 7, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 27, 2023 | Oct 17, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 27, 2023 | Sep 28, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2023 | Sep 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 27, 2023 | Oct 3, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 7, 2023 | Nov 16, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2023 | Nov 16, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 7, 2023 | Nov 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2023 | Nov 9, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2023 | Nov 13, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 16, 2023 | Nov 21, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 28, 2023 | Nov 28, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 29, 2023 | Dec 4, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $190,000
| Name | Role | License on permit |
|---|---|---|
| Marshall Bartz Schneider Schneder Design Associates | Architect | C29499 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026