1633 Valencia St
San Francisco permit 202212158402 · Bernal Heights
Mayor directive 13-01: to erect 6 stories, type 1a ground flr residential service & common spaces, type 3a upper flr residential units
- Filed
- Dec 15, 2022
- Issued
- Sep 19, 2023 (9 months after filing)
- Completed
- May 20, 2026 (32 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 197 stops across 8 departments
- Comments issued
- 44 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 15, 2022 | Dec 15, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 16, 2022 | Feb 7, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 16, 2022 | Aug 31, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 7, 2023 | May 16, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 7, 2023 | May 17, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 7, 2023 | Feb 8, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 7, 2023 | Mar 20, 2023 | — |
Public health review Public Health · HEALTH | Feb 7, 2023 | May 19, 2023 | — |
Public Health HEALTH-MH | May 11, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | May 16, 2023 | Jun 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 16, 2023 | Aug 3, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2023 | May 17, 2023 | — |
Public Health HEALTH-MH | May 19, 2023 | Jun 12, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 15, 2023 | Aug 10, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jun 15, 2023 | Jun 21, 2023 | — |
Public Health HEALTH-MH | Jun 15, 2023 | Jun 29, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2023 | Jun 20, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2023 | Jun 23, 2023 | — |
Development fee collection Building Inspection · DFCU | Aug 10, 2023 | Aug 10, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2023 | Sep 19, 2023 | Administrative |
Addendum 1: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 12, 2024 | Feb 21, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Feb 16, 2024 | Feb 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2024 | Feb 23, 2024 | Administrative |
Public health review Public Health · HEALTH | Feb 23, 2024 | Feb 27, 2024 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Feb 23, 2024 | Feb 28, 2024 | — |
Public health review Public Health · HEALTH | Feb 27, 2024 | Feb 27, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 28, 2024 | May 20, 2024 | Administrative |
Addendum 2: Foundation podium drill displacement columns
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 28, 2023 | Sep 29, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 29, 2023 | Oct 27, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 29, 2023 | Nov 16, 2023 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Sep 29, 2023 | Feb 16, 2024 | — |
Building plan review Building Inspection · BLDG | Nov 30, 2023 | Dec 18, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 30, 2023 | Dec 4, 2023 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Dec 14, 2023 | Jan 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 9, 2024 | Jan 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2024 | Jan 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 16, 2024 | Feb 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 16, 2024 | May 20, 2024 | Administrative |
Addendum 3: Superstructure (wood framed)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2023 | Oct 24, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Nov 14, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2023 | Nov 16, 2023 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Oct 24, 2023 | Jun 26, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 14, 2023 | Jan 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 14, 2023 | Jan 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 8, 2024 | Mar 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 8, 2024 | Apr 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 22, 2024 | Apr 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 13, 2024 | Jun 1, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 3, 2024 | Jun 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2024 | Jun 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 24, 2024 | Jun 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 24, 2024 | Jun 25, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 26, 2024 | Jun 28, 2024 | Administrative |
Addendum 4: Arch, mep, including civil and landscaping
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2023 | Oct 24, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Dec 13, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2023 | Nov 16, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 24, 2023 | Nov 11, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2023 | Nov 16, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2023 | Oct 25, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 24, 2023 | Oct 26, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 24, 2023 | Aug 12, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Oct 26, 2023 | Nov 6, 2023 | Issued Comments |
CON CON-BOND | Oct 30, 2023 | Feb 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 6, 2024 | Feb 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 6, 2024 | Feb 7, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 6, 2024 | Feb 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 6, 2024 | Feb 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2024 | Feb 27, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 6, 2024 | Feb 6, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2024 | Feb 8, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 14, 2024 | Jul 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 22, 2024 | Apr 11, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 22, 2024 | Mar 25, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 22, 2024 | Apr 4, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 22, 2024 | Mar 30, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 22, 2024 | Mar 25, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2024 | Mar 28, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2024 | Mar 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 14, 2024 | May 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2024 | May 15, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 14, 2024 | May 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 14, 2024 | May 17, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 14, 2024 | May 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 14, 2024 | May 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 14, 2024 | May 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 12, 2024 | Jun 28, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2024 | Jun 18, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 12, 2024 | Jun 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 12, 2024 | Jun 20, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2024 | Jun 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2024 | Jul 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 12, 2024 | Jun 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2024 | Jul 3, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 18, 2024 | Jul 18, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 18, 2024 | Jul 22, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 31, 2024 | Jul 31, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 7, 2024 | Aug 7, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2024 | Aug 14, 2024 | Administrative |
Addendum 5: Fire sprinkler
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 23, 2024 | Jul 26, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2024 | Jul 29, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Jul 26, 2024 | Jul 26, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 29, 2024 | Jul 31, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 29, 2024 | Sep 11, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 16, 2024 | Aug 22, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 6, 2024 | Sep 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2024 | Sep 11, 2024 | Administrative |
Addendum 6: Fire alarm elevator landing and two-way communication
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2024 | Dec 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2024 | Dec 18, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 18, 2024 | Feb 7, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 18, 2024 | Sep 22, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 16, 2025 | Jul 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 15, 2025 | Aug 17, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 20, 2025 | Sep 20, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Sep 22, 2025 | Sep 25, 2025 | Administrative |
Addendum 7: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 1, 2024 | Nov 18, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Nov 6, 2024 | Nov 6, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Nov 13, 2024 | Nov 13, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Nov 18, 2024 | Nov 18, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Nov 19, 2024 | Nov 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 19, 2024 | Dec 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 19, 2024 | Nov 22, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 19, 2024 | Dec 6, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 6, 2024 | Dec 9, 2024 | Administrative |
Addendum 8: Solar pv
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 4, 2025 | Apr 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2025 | Apr 21, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 22, 2025 | Apr 29, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 22, 2025 | May 6, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 22, 2025 | Jun 5, 2025 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jun 3, 2025 | Jun 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2025 | Jun 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2025 | Jun 18, 2025 | Administrative |
Addendum 9: Exterior building maintenance
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 10, 2024 | Dec 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2024 | Dec 19, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 19, 2024 | Dec 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 19, 2024 | Jan 2, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 19, 2024 | Dec 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 19, 2024 | Dec 23, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 19, 2024 | Jan 3, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2025 | Jan 8, 2025 | Administrative |
Addendum 10: Emergency responder radio coverage system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Dec 11, 2024 | Dec 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2024 | Dec 18, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 18, 2024 | Jan 21, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 18, 2024 | Aug 19, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 12, 2025 | Jul 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 19, 2025 | Aug 19, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2025 | Aug 28, 2025 | Administrative |
Addendum 11: Stormwater & plumbing horizontal wet vent only
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 13, 2024 | May 24, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 17, 2024 | May 17, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 23, 2024 | May 23, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 24, 2024 | May 24, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | May 29, 2024 | May 29, 2024 | Administrative |
Plumbing plan check Building Inspection · PID-PC | May 29, 2024 | Oct 4, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 29, 2024 | Oct 7, 2024 | Administrative |
Plumbing plan check Building Inspection · PID-PC | Oct 4, 2024 | Oct 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 7, 2024 | Oct 8, 2024 | Administrative |
Addendum 12: Evacuation signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 17, 2025 | Apr 30, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 2, 2025 | May 2, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | May 2, 2025 | May 5, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 2, 2025 | Jun 2, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | May 22, 2025 | Jun 2, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2025 | Jun 12, 2025 | Administrative |
Addendum 13: Rev1 to issued addendum 4
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 15, 2025 | May 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 28, 2025 | May 28, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 28, 2025 | May 29, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 28, 2025 | Jun 24, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 28, 2025 | Jun 3, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | May 28, 2025 | Jun 2, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | May 28, 2025 | Jun 2, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 28, 2025 | May 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2025 | Jun 2, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | May 28, 2025 | Jun 16, 2025 | Approved |
Plumbing plan check Building Inspection · PID-PC | May 28, 2025 | Jun 5, 2025 | Approved |
Public Health HEALTH-MH | May 28, 2025 | Jun 11, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | May 28, 2025 | Jul 9, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 25, 2025 | Jun 25, 2025 | Approved |
Public Health HEALTH-MH | Jun 26, 2025 | Jul 8, 2025 | Not Applicable |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 9, 2025 | Jul 9, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 9, 2025 | Jul 10, 2025 | Administrative |
Addendum 14: Rev1 to issued addendum 9
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 24, 2025 | Jul 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2025 | Jul 8, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jul 8, 2025 | Jul 28, 2025 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Jul 8, 2025 | Jul 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 8, 2025 | Jul 9, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 8, 2025 | Sep 17, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Sep 17, 2025 | Sep 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2025 | Sep 19, 2025 | Administrative |
Addendum 15: Rev1 to issued addendum 8 - solar pv
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 21, 2025 | Aug 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 29, 2025 | Aug 29, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Aug 29, 2025 | Sep 11, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Aug 29, 2025 | Sep 12, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Aug 29, 2025 | Sep 16, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 29, 2025 | Nov 12, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 3, 2025 | Nov 3, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 3, 2025 | Nov 7, 2025 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Nov 3, 2025 | Nov 5, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 12, 2025 | Nov 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $53,000,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Elias Simons David Baker Architects | Architect | C-30025 |
| Emmanuel Kai Ming Pun Puns And Associates, Inc. | Engineer | S2883 |
| Randall James Girouard Access System & Solutions Inc | Engineer | S-5357 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026