464 Hill St
San Francisco permit 202212198613 · Noe Valley
Horizontal and vertical addition. interior remodel throughout, minor exterior alterations & addition, and rear yard alterations to an existing 3-story + mezzanine. single-family residence.
- Filed
- Dec 19, 2022
- Issued
- Jun 11, 2024 (18 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 43 stops across 6 departments
- Comments issued
- 10 times, by Building Inspection, Planning, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 19, 2022 | Dec 22, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 23, 2022 | Nov 14, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 23, 2022 | Jun 5, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jul 17, 2023 | Jul 20, 2023 | — |
Zoning review Planning · CP-ZOC | Nov 14, 2023 | Nov 14, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 14, 2023 | Dec 26, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2023 | Nov 15, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2023 | Dec 21, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 8, 2023 | Dec 20, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 8, 2023 | Dec 8, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 18, 2023 | Feb 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 13, 2024 | Feb 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 7, 2024 | Mar 19, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 21, 2024 | Mar 22, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 21, 2024 | Mar 21, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 26, 2024 | Mar 26, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 1, 2024 | May 1, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 2, 2024 | May 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 2, 2024 | May 14, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 2, 2024 | May 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 22, 2024 | May 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 22, 2024 | May 23, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 22, 2024 | May 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 22, 2024 | Jun 5, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2024 | May 28, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2024 | Jun 11, 2024 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 18, 2026 | Jul 7, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2026 | Jul 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 20, 2026 | Jul 28, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 20, 2026 | Sep 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 20, 2026 | Sep 25, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 20, 2026 | Aug 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 20, 2026 | Jul 28, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2026 | Jul 21, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 20, 2026 | Aug 24, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 20, 2026 | Aug 5, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 20, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Oct 13, 2026 | Nov 3, 2026 | Approved |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $1,250,000
| Name | Role | License on permit |
|---|---|---|
| Eric M Dumican Dumican & Mosey Architects | Architect | C31398 |
| David M Strandberg Strandberg Engineering | Engineer | 62993 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021