3995 Alemany Bl
San Francisco permit 202212198693 · Oceanview/Merced/Ingleside
Ste #4001:change of occupancy. tenant improvement of (e) fitness center to new houseware sales market (h mart extension) at basement & ground level (potential tenant at ground level in separate permit).
- Filed
- Dec 19, 2022
- Issued
- Apr 17, 2024 (16 months after filing)
- Completed
- Mar 13, 2026 (23 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 46 stops across 5 departments
- Comments issued
- 16 times, by Building Inspection, Public Utilities, Fire Department
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 19, 2022 | Dec 22, 2022 | Administrative |
Permit Processing Center Building Inspection · PPC | Dec 22, 2022 | Mar 27, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 23, 2022 | Sep 18, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 18, 2023 | Dec 5, 2023 | In Progress |
Structural plan approval Building Inspection · PAD-STR | Sep 18, 2023 | Oct 31, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 18, 2023 | Nov 7, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 18, 2023 | Oct 2, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 18, 2023 | Oct 11, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Sep 18, 2023 | Nov 7, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 25, 2023 | Oct 6, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2023 | Dec 5, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 26, 2023 | Jan 4, 2024 | In Progress |
Structural plan approval Building Inspection · PAD-STR | Dec 26, 2023 | Dec 28, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 26, 2023 | Dec 28, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Dec 26, 2023 | Jan 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2023 | Jan 2, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 26, 2023 | Dec 27, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 26, 2023 | Dec 27, 2023 | Approved |
Public health review Public Health · HEALTH | Dec 26, 2023 | Dec 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 5, 2024 | Jan 19, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2024 | Jan 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 31, 2024 | Feb 14, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 31, 2024 | Feb 1, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jan 31, 2024 | Feb 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 31, 2024 | Feb 5, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 31, 2024 | Feb 21, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 31, 2024 | Feb 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 31, 2024 | Feb 5, 2024 | Approved |
Public health review Public Health · HEALTH | Jan 31, 2024 | Feb 1, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2024 | Feb 1, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 9, 2024 | Feb 9, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 20, 2024 | Feb 20, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 21, 2024 | Mar 13, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 21, 2024 | Feb 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 21, 2024 | Feb 26, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 21, 2024 | Mar 1, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 21, 2024 | Feb 27, 2024 | Approved |
Public health review Public Health · HEALTH | Feb 21, 2024 | Mar 20, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 11, 2024 | Mar 11, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 11, 2024 | Mar 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2024 | Mar 15, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 11, 2024 | Mar 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2024 | Mar 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 11, 2024 | Mar 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 20, 2024 | Mar 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2024 | Apr 17, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $2,213,066
| Name | Role | License on permit |
|---|---|---|
| Seong Bae Kim Corbel Architects | Architect | C23320 |
| Hong Kook Kim Basis Engineering | Engineer | C64529 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2018