1901 Jerrold Av
San Francisco permit 202212208746 · Bayview Hunters Point
To erect a 1-story, type vb, s2 warehouse building.
- Filed
- Dec 20, 2022
- Issued
- Mar 9, 2026 (39 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 91 stops across 7 departments
- Comments issued
- 18 times, by Planning, Building Inspection, Public Works, Fire Department, Public Utilities, Public Health
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 20, 2022 | Dec 21, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 22, 2022 | Sep 15, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 22, 2022 | Jan 20, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 7, 2023 | Dec 18, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 3, 2023 | May 24, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2023 | Apr 5, 2023 | — |
Urban forestry Public Works · DPW-BUF | Apr 3, 2023 | Jul 3, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 3, 2023 | Dec 20, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2023 | Jul 25, 2023 | — |
Public health review Public Health · HEALTH | Apr 3, 2023 | Apr 3, 2023 | — |
Public health food review Public Health · HEALTH-FD | Apr 3, 2023 | Apr 4, 2023 | Approved |
Zoning review Planning · CP-ZOC | Jun 5, 2025 | Sep 18, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 5, 2025 | Jul 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2025 | Jun 12, 2025 | Not Applicable |
Fire prevention review Fire Department · SFFD | Jun 5, 2025 | Jun 12, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2025 | Jun 5, 2025 | Issued Comments |
Public Health HEALTH-MH | Jun 5, 2025 | Jun 10, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Jun 5, 2025 | Jun 5, 2025 | Approved |
Public Health HEALTH-MH | Jun 10, 2025 | Jun 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 17, 2025 | Sep 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 17, 2025 | Oct 6, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Sep 17, 2025 | Oct 8, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 17, 2025 | Oct 21, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2025 | Sep 25, 2025 | Approved |
Public Health HEALTH-MH | Sep 17, 2025 | Sep 18, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Sep 17, 2025 | Sep 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 21, 2025 | Oct 21, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 5, 2025 | Nov 5, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Nov 13, 2025 | Nov 20, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 13, 2025 | Nov 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 13, 2025 | Nov 17, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Nov 13, 2025 | Nov 13, 2025 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Nov 13, 2025 | Nov 18, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 13, 2025 | Nov 14, 2025 | Approved |
Public Health HEALTH-MH | Nov 13, 2025 | Nov 13, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Nov 13, 2025 | Nov 13, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 16, 2025 | Dec 16, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 18, 2025 | Dec 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 18, 2025 | Dec 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 18, 2025 | Dec 31, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Dec 18, 2025 | Dec 31, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 18, 2025 | Dec 30, 2025 | Approved |
Public Health HEALTH-MH | Dec 18, 2025 | Dec 22, 2025 | Approved |
Public health food review Public Health · HEALTH-FD | Dec 18, 2025 | Dec 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jan 2, 2026 | Jan 6, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jan 2, 2026 | Jan 5, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 2, 2026 | Jan 5, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jan 2, 2026 | Jan 20, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Jan 2, 2026 | Jan 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 2, 2026 | Jan 5, 2026 | Approved |
Public Health HEALTH-MH | Jan 2, 2026 | Jan 9, 2026 | Approved |
Public health food review Public Health · HEALTH-FD | Jan 2, 2026 | Jan 6, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jan 20, 2026 | Jan 20, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 20, 2026 | Mar 9, 2026 | Administrative |
Addendum 1: Soil improvement, health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 1, 2026 | Apr 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 13, 2026 | Apr 13, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 13, 2026 | May 12, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2026 | May 12, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2026 | Apr 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 13, 2026 | May 28, 2026 | Approved |
Public Health HEALTH-MH | Apr 13, 2026 | Apr 15, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 13, 2026 | Oct 20, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jun 30, 2026 | Jun 30, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2026 | Oct 5, 2026 | Not Applicable |
Urban forestry Public Works · DPW-BUF | Sep 23, 2026 | Oct 19, 2026 | Approved |
Public Health HEALTH-MH | Sep 23, 2026 | Sep 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2026 | In progress | — |
Addendum 2: Grading/foundations
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 1, 2026 | Apr 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 13, 2026 | Apr 13, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 13, 2026 | May 23, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2026 | May 23, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 13, 2026 | Jul 17, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2026 | Apr 15, 2026 | Approved |
Public Health HEALTH-MH | Apr 13, 2026 | Apr 15, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 13, 2026 | In progress | Administrative |
Building plan review Building Inspection · BLDG | Jun 30, 2026 | Jun 30, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2026 | Oct 5, 2026 | Issued Comments |
Public Health HEALTH-MH | Sep 23, 2026 | Sep 23, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 1, 2026 | Apr 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 13, 2026 | Apr 13, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 13, 2026 | May 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2026 | May 23, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 13, 2026 | Jul 17, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2026 | Apr 15, 2026 | Issued Comments |
Public Health HEALTH-MH | Apr 13, 2026 | Apr 15, 2026 | Administrative |
Permit Processing Center Building Inspection · PPC | Apr 13, 2026 | Oct 6, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 1, 2026 | Jul 1, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2026 | Oct 5, 2026 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Oct 6, 2026 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $26,000,000
| Name | Role | License on permit |
|---|---|---|
| Brian H Liles Jackson Liles Architecture | Architect | C27249 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026